暨南大学项目管理chapter 8 scheduling resources and costs.ppt
《暨南大学项目管理chapter 8 scheduling resources and costs.ppt》由会员分享,可在线阅读,更多相关《暨南大学项目管理chapter 8 scheduling resources and costs.ppt(73页珍藏版)》请在三一办公上搜索。
1、管理学院 School of Management,佟瑞 Edward Tong,MPM,MBA,2023/11/18,1,Edward TongCopyright reserved Jinan University,83,Where We Are Now,84,The Resource Problem,Resources and PrioritiesProject network times are not a schedule until resources have been assigned.The implicit assumption is that resources will
2、be available in the required amounts when needed.Adding new projects requires making realistic judgments of resource availability and project durations.Cost estimates are not a budget until they have been time-phased.,85,Project Planning Process,FIGURE 8.1,86,The Resource Problem(contd),Resource Smo
3、othing(or Leveling)Involves attempting to even out varying demands on resources by using slack(delaying noncritical activities)to manage resource utilization when resources are adequate over the life of the project.Resource-Constrained SchedulingThe duration of a project may be increased by delaying
4、 the late start of some of its activities if resources are not adequate to meet peak demands.,87,Types of Project Constraints,Technical or Logic ConstraintsConstraints related to the networked sequence in which project activities must occur.Physical ConstraintsActivities that cannot occur in paralle
5、l or are affected by contractual or environmental conditions.Resource ConstraintsThe absence,shortage,or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activitiesKinds of Resource ConstraintsPeople,materials,equipment,88,Constrai
6、nt Examples,FIGURE 8.2,89,Classification of A Scheduling Problem,Classification of ProblemUsing a priority matrix will help determine if the project is time or resource constrained.Time-Constrained ProjectMust be completed by an imposed date.Time is fixed,resources are flexible:additional resources
7、are required to ensure project meets schedule.Resource-Constrained ProjectIs one in which the level of resources available cannot be exceeded.Resources are fixed,time is flexible:inadequate resources will delay the project.,810,Resource Allocation Methods,Limiting AssumptionsSplitting activities is
8、not allowedonce an activity is start,it is carried to completion.Level of resources used for an activity cannot be changed.Risk AssumptionsActivities with the most slack pose the least risk.Reduction of flexibility does not increase risk.The nature of an activity(easy,complex)doesnt increase risk.,8
9、11,Resource Allocation Methods(contd),Time-Constrained ProjectsMust be completed by an imposed date.Require use of leveling techniques that focus on balancing or smoothing resource demands.Use positive slack(delaying noncritical activities)to manage resource utilization over the duration of the proj
10、ect.Peak resource demands are reduced.Resources over the life of the project are reduced.Fluctuation in resource demand is minimized.,812,Botanical Garden,FIGURE 8.3,813,Resource Allocation Methods(contd),Resource Demand Leveling Techniques for Time-Constrained ProjectsAdvantagesPeak resource demand
11、s are reduced.Resources over the life of the project are reduced.Fluctuation in resource demand is minimized.DisadvantagesLoss of flexibility that occurs from reducing slack.Increases in the criticality of all activities.,814,Resource Allocation Methods(contd),Resource-Constrained ProjectsResources
12、are limited in quantity or availability.Activities are scheduled using heuristics(rules-of-thumb)that focus on:Minimum slackSmallest(least)durationLowest activity identification numberThe parallel method is used to apply heuristicsAn iterative process starting at the first time period of the project
13、 and scheduling period-by-period the start of any activities using the three priority rules.,815,Resource-Constrained Schedule through Period 23,FIGURE 8.4,816,Resource-Constrained Schedule through Period 23,FIGURE 8.4(contd),817,Resource-Constrained Schedule through Period 23,FIGURE 8.4(contd),818,
14、Resource-Constrained Schedule through Period 56,FIGURE 8.5,819,Resource-Constrained Schedule through Period 56,FIGURE 8.5(contd),820,Resource-Constrained Schedule through Period 56,FIGURE 8.5(contd),821,Computer Demonstration of Resource-Constrained Scheduling,EMR ProjectThe development of a handhel
15、d electronic medical reference guide to be used by emergency medical technicians and paramedics.ProblemThere are only eight design engineers who can be assigned to the project due to a shortage of design engineers and commitments to other projects.,822,EMR Project:Network View Schedule before Resour
16、ces Leveled,FIGURE 8.6,823,EMR Project before Resources Added,FIGURE 8.7,824,EMR ProjectTime Constrained Resource Usage View,January 1523,FIGURE 8.8A,825,Resource Loading Chart for EMR Project,January 1523,FIGURE 8.8B,826,EMR Project Network View Schedule after Resources Leveled,FIGURE 8.9,827,EMR P
17、roject Resources Leveled,FIGURE 8.10,828,The Impacts of Resource-Constrained Scheduling,Reduces delay but reduces flexibility.Increases criticality of events.Increases scheduling complexity.May make the traditional critical path no longer meaningful.Can break sequence of events.May cause parallel ac
18、tivities to become sequential and critical activities with slack to become noncritical.,829,Splitting,SplittingA scheduling technique use to get a better project schedule and/or increase resource utilization.Involves interrupting work on an activity to employ the resource on another activity,then re
19、turning the resource to finish the interrupted work.Is feasible when startup and shutdown costs are low.Is considered the major reason why projects fail to meet schedule.,830,Splitting Activities,FIGURE 8.11,831,Benefits of Scheduling Resources,Leaves time for consideration of reasonable alternative
20、s:Cost-time tradeoffsChanges in prioritiesProvides information for time-phased work package budgets to assess:Impact of unforeseen eventsAmount of flexibility in available resources,832,Multiproject Resource Schedules,Multiproject Scheduling ProblemsOverall project slippageDelay on one project creat
21、e delays for other projectsInefficient resource applicationThe peaks and valleys of resource demands create scheduling problems and delays for projects.Resource bottlenecksShortages of critical resources required for multiple projects cause delays and schedule extensions.,833,Multiproject Resource S
22、chedules(contd),Managing Multiproject Scheduling:Create project offices or departments to oversee the scheduling of resources across projects.Use a project priority queuing system:first come,first served for resources.Centralize project management:treat all projects as a part of a“megaproject.”Outso
23、urce projects to reduce the number of projects handled internally.,834,Direct Labor Budget Rollup($000),FIGURE 8.12,835,Time-Phased Work Package Budget(Labor Cost Only),FIGURE 8.13,836,Two Time-Phased Work Packages(Labor Cost Only),FIGURE 8.14,837,Patient Entry Project Network,FIGURE 8.15,838,Patien
24、t Entry Time-Phased Work Packages Assigned,FIGURE 8.16,839,CEBOO Project Monthly Cash Flow Statement,FIGURE 8.17,840,CEBOO Project Weekly Resource Usage Schedule,FIGURE 8.18,841,Key Terms,HeuristicPlanned value(PV)Resource-constrained projectsSmoothingSplittingTime-constrained projectsTime-phased bu
25、dget baseline,1,Delaying noncritical activities to lower peak demand on resources is known as resourceA.ShiftingB.EffectivenessC.ManipulatingD.Resource smoothingE.Allocation,2023/11/18,Edward TongCopyright reserved Jinan University,42,2.,If resources are not adequate to meet peak demands,the resulti
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 暨南大学项目管理chapter scheduling resources and costs 暨南大学 项目 管理 chapter

链接地址:https://www.31ppt.com/p-6614371.html