WI871081000021 Rev.00 蒸汽轮机及发电机吊装.doc
《WI871081000021 Rev.00 蒸汽轮机及发电机吊装.doc》由会员分享,可在线阅读,更多相关《WI871081000021 Rev.00 蒸汽轮机及发电机吊装.doc(29页珍藏版)》请在三一办公上搜索。
1、CSPC Nanhai Petrochemicals ProjectSEPCO Electric Power Construction CorpCSPC NANHAI PETROCHEMICALS PROJECTCSPC 南 海 石 化 项 目蒸汽轮机及发电机吊装STEAM TURBINE AND GENERATOR HANDLINGWORK INSTRUCTION: WI-8710-8100-0021SEPCO Electric Power Construction Corporation山东电力基本建设总公司 REV版次DATE日期REASON FOR ISSUE修订原因BY编制CHKD审
2、核REVIEW审查APPR批准A23.Mar.2004Issued for ApprovalGongXiYuGUANYIXIAOTPTIANGHB22.Apr.2004Issued for ApprovalGongXiYuGUANYIXIAOTPTIANGHC10.JUN.2004Issued for ApprovalGongXiYuGUANYIXIAOTPTIANGH0024.JUN.2004Issued for UseGongXiYuGUANYIXIAOTPTIANGHRevision informationRevDate Section No.Description of main ch
3、angesA23.Mar.2004 All初版First issueB22.Apr.2004All翻译为中英文对照Translation to englishC10.JUN.2004 13.根据PMC 审核意见进行修改according to PMC comments modification0024.JUN.2004 9.2澄清每个千斤顶使用9根钢索confirm 9 strands in the each jack 9.7.3;9.8.3增加吊板现场修改的有关内容add: modification for the lifting plate on site 目 录content1.0 范围
4、 scope 2.0 目的 purpose 3.0 职责 responsibilities 4.0 概述 general 5.0 编制依据 6.0 施工准备 references7.0 主要施工机械、工器具 major construction machines, tools8.0 劳动力组织 labor force9.0 施工工序和施工方法 process and method10. 相关计算书 related calculation11. 措施性材料清单 measure materials list12. 附图 attached sketch13. 附录attachment14工作安全分析
5、(JSA) 1.0 范围:scope本程序适用于南海石化项目汽电联产部分汽机房内四台蒸汽轮机和发电机的吊装就位。主要包括:液压提升装置的安装;发电机的吊装就位;汽轮机的吊装就位;液压提升装置的拆除。This instruciton applies to lifting and postioning of 4 STs and generators in ST house, including:Installation of hydraulic lift unit,Lifting and positioning of generators,Lifting and positioning of ST
6、s,Removal of hydraulic lift unit.2.0 目的:purpose编制本程序旨在为了保证汽轮机和发电机的吊装工作安全顺利进行。To ensure the lifting and positioning to be taken safely and smoothly. 3.0 职责:responsibilities3.1 sepco1负责全部的吊装工作。Sepco1 for all lifting and positioning.3.2 SEPCO负责协调和质量验收工作。 Sepco for coordination and quality/inspection.4.
7、0 概述:general 4.1本项目汽机房内设计安装四台机组,顺列布置在汽机房+18.00m(绝对标高)运转层上,蒸汽轮机台板底部标高为+18.00m,发电机台板底部标高为+18.780m,且发电机基础周围有一标高为+18.890m的台阶;发电机朝向扩建端(1柱);蒸汽轮机和发电机均由SIEMENS AG公司制造供货。4 units designed to be arranged in sequence on the running level (elevation: +18.00m) of ST house. The bottom elevation of ST table is +18.
8、00m, and the bottom elevation of generator is +18.780m. STs and generators supplied by SIEMENS AG.4.2 汽轮机和发电机均为组装在一个底板上,整体组装模块式供货;除个别无法包装在整个模块之内外露的、超过规定高度的部件,需拆掉单独运输。Turbine and generator on baseframes are delivered essentially complete. For shipping, only those parts are dismantled which protrude s
9、ideways from the baseframe or which exceed the specified height.4.3设备主要尺寸及重量Major dimension and weight of equipmentDescriptionDimension(l*w*h)Transport Weight(t)Steam turbine8964*5900*4124148Generator 8027*3700*2921112.64.4四台机组的汽轮机、发电机使用一台200t液压提升装置进行吊装。1 of 200t hydraulic lift unit for lifting STs
10、and generators of 4 groups.5.0 编制依据:references5.1 设备厂家SIEMENS AG公司提供的有关图纸资料;Related drawings from SIEMENS AG.5.2 DL5011-92 电力建设施工及验收规范(汽轮机组篇);Electrical power construction and acceptance specification-ST 5.3火电施工质量检验给评定标准(汽机篇) 1998版Power construction quality inspection and evaluation- ST 19985.4 设计施工
11、图纸;Design construction drawings5.5 有关的DEP和SP Related DEP and SP5.6液压提升装置有关图纸Hydraulic lift unit drawings6.0 施工准备:preparation6.1汽轮发电机基础已施工完毕并办理交接手续。基础准备工作已完成。基础准备工作主要包括以下内容:The foundations have been completed and handed over. Concrere foundation preparation as follows:l 基础表面清理干净,无油脂等杂物。concrete surfa
12、ce which are to be grouted in the course of installation must be free of loose particles and from weakly adhering cement wash and must be free from dust ,grease and oil.l 划好纵横中心线,并确定标高控制点。Establish machine longitudinal and transverse axes and elevation and mark the position of the leveling plates.l
13、将调整垫板按照图纸规定位置布置好,(临时支撑垫板的尺寸要比正式调整垫板的尺寸大)。所有的垫板必须水平,且标高符合要求。Set the leveling plates (approximately 30mm thick )in grout at the marked positions.(the leveling plates used as temporary support points are larger than the standard leveling plates and incorporate jacking screws.) the top surfaces must be
14、level ,and all at the same height if at all possible .check height against the elevation datum point provide or against the installation plan or against a machine that the turbine is to be aligned to .l 将需要灌浆的位置进行灌浆,安装汽轮机灌浆模板。Partition the surfaces to be grouted ,and install permanent formwork if ne
15、cessary.l 用垫片调整临时支撑点A1 to A4的标高,使其标高比设备的正常就位后的标高低1mm左右。Shim the leveling plates for the temporary support points “A1 to A4”(see layout drawing )such that their top surface are at uniform height. The height should be 1 mm lower than required after the turbine set down on the foundation .l 其余有关要求详见由SI
16、MENS提供的安装手册。Other requirements refer to the ERECTION MANUAL STEAM TURBINE by SIMENS.6.2施工人员应熟悉有关图纸及本作业指导书,了解吊装程序并经技术、安全交底。Personnel shall be familiar with related drawings and this work instruction and lifting procedure, and safety issues to be instructed.6.3汽机房行车已投用。ST hall travelling crane availab
17、le. 6.4汽机房固定端18至20柱以西20m范围内之间的场地平整夯实,标高为+6.770m。The ground from column 18# to 20# in row A and B of ST house has been compacted and level, and its elevation +6.770m.6.5汽机房18-#20轴线之间屋架缓装;固定端的山墙缓装。Roof structure between axis 18# and 20# pending, and wall structure of fixed side pending.7.0主要施工机械、工器具ma
18、jor construction equipment and tools7.1 主要施工机械major construction equipment汽机房行车 40/10t ST hall travelling crane 1台CX1800 180t履带吊 crawler crane 1台 20t运输车 truck 1台50t汽车吊 truck crane 1台30t龙门吊 gantry crane 1台7.2 主要工器具、吊索具 main tools序号item名称description规格specification数量qty备注remarks1卷尺tape30m1把2敲击扳手、电动扳手st
19、rike and electrical spanners各1套1 set of each type3磨光机grinders2台4钢卷尺steel tapes30m;5m各1套1 set of each type5钢板尺steel ruler1m1把6线锤plumbL=10m2只7撬棒tommy bar3212003根8电、火焊工具electrical and flame welding tools各1套1 set of each type8.0劳动力组织 labor force 总指挥: 一名 1 supervisor chief技术负责人: 一名 1 technical leader质量负责
20、人: 一名 1 quality leader施工负责人: 一名 1 construction leader安装工: 八名 8 erectors起重工: 四名(含起重指挥1名)4 lifters including 1 conductor电焊工: 一名 1 welder架工: 四名 4 scaffold erectors液压系统操作工: 五名 (含操作指挥1名) 5 hydraulic system operater including 1 conductor吊车操作工: 三名 3 crane operater9.0施工工序及施工方法process and method9.1施工工序proces
21、s 提升装置安装#1发电机、汽轮机吊装就位2发电机、汽轮机吊装就位 3发电机、汽轮机吊装就位 4发电机、汽轮机吊装就位 提升装置拆除 installation of lift unit 1# generator and ST lifting and positioning 2# generator and ST lifting and positioning 3# generator and ST lifting and positioning 4# generator and ST lifting and positioning dismantling of lift unit9.2 提升装
22、置有关数据related data for lift unitl 汽轮机、发电机的吊装使用国电电力建设研究所设计、山东丰汇设备技术有限公司制造的200t液压提升吊装架装置进行吊装。吊装架主要由固定架、移动架、吊板、泵站、吊杆、千斤顶、下锚头吊架等组成。详见附图B。有关技术参数如下:200t hydraulic lift unit fabricated by Shandong Fenghui Equipment Co. Ltd. Is to be applied for lifting STs and generators, which including fixed structure, mo
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- WI871081000021 Rev.00 蒸汽轮机及发电机吊装 Rev 00 蒸汽 轮机 发电机 吊装

链接地址:https://www.31ppt.com/p-5075144.html