建筑环境与能源应用工程专业英语.ppt
《建筑环境与能源应用工程专业英语.ppt》由会员分享,可在线阅读,更多相关《建筑环境与能源应用工程专业英语.ppt(26页珍藏版)》请在三一办公上搜索。
1、,Unit FifteenCommissioning of Variable Air Volume Systems,What is Commissioning(Cx)?,Definition:“A quality-focused process for enhancing the delivery of a project.The process focuses on verifying and documenting that the facility and all of its systems and assemblies are planned,designed,installed,t
2、ested,operated,and maintained to meet the Owners Project Requirements.”ASHRAE Guideline 0-2005,The Commissioning Process,Commissioning is often performed by an independent third-party engineering company.Operates as an owners representative to insure the installed systems meet the owners requirement
3、s and the plans and specificationsUsually hired by the owner,sometimes by the architect,or general contractor.,Commissioning Person,All participants in the construction project have a commissioning responsibility.Participants include the commissioning authority,owner,design professionals,constructio
4、n manager,general contractor,subcontractors,operation and maintenance manager,suppliers,and equipment manufacturers.,Benefits of Commissioning,Reduced change ordersLess warranty and callbacks for contractorSmoother turnover to maintenanceImproved equipment reliabilityReduced IEQ problems Reduced occ
5、upant complaintsImproved productivityCorrect system operation and installationFacility meets Owners expectation and operational needsReduced utility consumption and operational costs,Commissioning Objectives Ensure the facility meets the owners performance requirements Provide a safe and healthy env
6、ironment Provide optimum energy performance Provide a facility that can be efficiently operated and maintained Provide complete orientation and training to facility staff and occupants Provide improved documentation of system characteristics,Commissioning-What did we use to do and why do we need it?
7、CX of mechanical and electrical systems was done by the installing contractors No standardization,or clear approach Most of the real CX occurred during the warranty period as warranty calls Buildings operated less efficiently First year of occupancy was frustrating for the owner Contractors spent mo
8、re money during the warranty periods Contractors can be rushed without enough time to double-check their work Design Engineers do not have enough budget to oversee the construction in detail Owners have had bad experiences with prolonged project closeout,and see CX as a solution Hold contractors acc
9、ountable for the specifications,Commissioning Scope,Mechanical SystemsAll HVAC equipmentBuilding automation system and hardwired controlsElectrical SystemsSwitchgear,major disconnects,backup generators and UPS(Uninterrupted Power Supply)Fire Safety SystemsSecurity SystemsKitchen equipmentIrrigation
10、systemLaboratory Fume hoods,gas control,Commissioning and Construction Phases,Other Types of Commissioning,Retro-commissioningPerformed to existing buildings that have not previously been commissioned,after they have been occupiedUsually instigated as a result of high energy bills or poor occupant c
11、omfortRecommissioningPerformed 5 to 10 years after a building was previously commissionedSometime used as a form of deferred maintenance,Variable Air Volume(VAV)use of varying airflow to control the condition of air,in contrast to the use of constant flow(often)with varying temperature.VAV system co
12、ntrols temperature in a space by varying the quantity of supply air rather than varying the supply air temperature.A VAV terminal unit at the zone varies the quantity of supply air to the space.The supply air temperature is held relatively constant:while supply air temperature can be moderately rese
13、t depending on the season,it must always be low enough to meet the cooling load in the most demanding zone,and to maintain appropriate humidity.,Why use VAV?,Provides multiple zones of comfortLife cycle cost will be less than other HVAC Systems trying to accomplish similar comfort levelsLoad diversi
14、tySmaller equipment(lower AC unit first cost compared to Constant Volume)Less supply air(less energy consumption)Able to adapt to changes in building use,Why Not?,Higher first cost than comparable single zone Controls,equipment,commissioningIncreased maintenance costMore pieces to look after,Constan
15、t volume-variable temperature system have been dominating the HVAC applications in the past for obvious reasons.The implementation of variable volume control has been done with dampers or other mechanical control methods.The advantages of variable air volume system implemented with variable speed co
16、ntrol are:Fast control to keep the comfort zone limits Low consumption of electrical energy Lower consumption of heating and cooling energy than in constant air volume systems Simpler to keep noise level down,1.Introduction2.Commissioning method statement3.System components 4.Preliminary checks5.Com
17、missioning sequence 6.Setting to work 7.Terminal units 8.Secondary air distribution9.Return air spigots 10.System diversity 11.Fan design performance check 12.System performance checks,Frequently used words and phrases:Variable air volume(VAV)system 变风量系统commissioning 试运行 调试 air volume flow rate 空气体
18、积流量terminal unit 终端设备 flexible duct 柔性风管Pitot tube 毕托管 thermal anemometer 热线风速仪supply fan 送风风机 extract fan 排风机over-pressurization 压力过高 spigot 套管、栓、龙头,1.Variable air volume(VAV)systems are dynamic air distribution systems and,as their name implies,the air volume flow rate is varied according to vario
19、us parameters to achieve the required design conditions.2.The fact that VAV systems are designed to vary system performance imposes a number of specific tasks on the commissioning specialist,which must be carried out in order to achieve satisfactory overall performance.3.Proprietary units may employ
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 建筑 环境 能源 应用 工程 专业 英语
链接地址:https://www.31ppt.com/p-4910773.html