汽轮机辅助设备安装方案 (中英文).docx
《汽轮机辅助设备安装方案 (中英文).docx》由会员分享,可在线阅读,更多相关《汽轮机辅助设备安装方案 (中英文).docx(28页珍藏版)》请在三一办公上搜索。
1、汽轮机辅助设备安装作业指导书施工作业指导书审批表ApprovalFormforConstructionMethodology作业项目名称Jobname汽轮机辅助设备安装作业指导书InstallationInstructionsforSteamTurbineAuxiliaryEquipment编号No.编制Preparedby签名signature:日期date:专业审核Departmentreview签名signature:日期date:项目审批ReviewedandApprovedbyprojectdepartment工程engineering签名signature:日期date:质量qua
2、lity签名signature:日期date:安监Safetysupervision签名signature:日期date:总工ChiefEngineer签名signature:日期date:目录Contents1.0编制依据Reference12.0概述Summary13.0主要工作量Mainworkquantity24.0作业条件Workcondition35.0作业方案Workscheme56.0强制性条文执行内容COntentofcompulsoryprovisionsofengineeringconstructionstandards77.0安全文明施工保障措施及风险控制计划表Safe
3、tyandcivilizationconstructionguaranteemeasuresandriskcontrolplanlist88.0质量控制措施QIIalitycontrolmeasures219.0绿色施工措施Greenconstructionmeasures2210.0应急保障措施Emergencysupportmeasures231.0编制依据Reference1.1 电力建设施工技术规范第3部分:汽轮发电机组DL5190.32012;TechnicalspecificationforthermalpowererectionandconstructionPart3:Steam
4、turbineunitDL51903-2012;1.2 电力建设施工质量验收及评价规程第3部分:汽轮发电机组DL/T5210.3-2018;CodeforconstructionqualityacceptanceandevaluationforelectricpowerconstructionPart3:SteamturbineunitDL/T5210.3-2018:1.3 电力建设安全工作规程第1部分:火力发电厂DL5009.1-2012;Codeofsafetyoperationinpowerengineeringconstructionpart1:thermalpowerplantDL5
5、009.1-2012;1.4 工程建设标准强制性条文电力工程部分(2011版);Thecompulsoryprovisionsofengineeringconstructionstandards,electricpowerengineering(2012)1.5 MHPS提供的图纸及技术文件资料;DrawingsandtechnicaldocumentsprovidedbyMHPS.1.6 浙江省电力设计院有限公司相关图纸;RelevantdrawingsprovidedbyZhejiangElectricPowerdesigninstituteCo.Itd;1.7 孟加拉国库尔纳项目部汽机专
6、业施工组织设计。ProfessionalconstructionorganizationdesignforsteamturbinesOfBangladeshKhulnaProjectDepartment2.0概述Summary本工程位于孟加拉国库尔纳市北部约6公里处,Bhairab河南岸。本工程为燃油/燃气双燃料双轴联合循环发电项目,本台工程设计安装一套GE公司生产的9F.03燃气轮发电机组,为新建1套9F.03AGP燃气轮发电机组、1套余热锅炉、1台汽轮机。Thisprojectislocatedabout6kilometersnorthofKhulnaCity,Bangladesh,ont
7、hesouthbankoftheBhairabRiveThisprojectisanoil/gasdual-fueldual-shaftcombinedcyclepowergenerationproject.Thisprojectisdesignedtoinstalla9E03gasturbinegeneratorsetproducedbyGE,whichisanewsetof9E03AGPgasturbinegeneratorsetand1setofwasteheatBoiler,1steamturbine.汽轮机辅助设备列表如下:Thelistofsteamturbineauxiliary
8、equipmentisasfollows:序号No.名称NAME单位UNIT数量QITY支撑面标高BEARINGSURFACEELEVATION1润滑和液压油箱LUBEANDHYDRAULICTANKSET1V0.02离心式油净化装置CENTRIFUGALOILPURIFSET1vo.o3真空泵VACUUMPUMPSET2vo.o4胶球泵RUBBERCLEANINGPUMPSET2vo.o5装球室BALLCOLLECTORSET2vo.o6凝结水泵CONDENSATEPUMPSET3V-2.477疏水扩容器坑疏水泵DRAINFLASHTANKPITDRAINPUMPSET2V-3.808疏水扩
9、容器DRAINFLASHTANKSET1V-3.09轴封冷却器GLANDSEALCONDENSERSET13.5010#1低压加热器LPlHEATERSET1vo.o11#2低压加热器LP2HEATERSET1vo.o12本体疏水扩容器PROPERDRAINFLASHTANKSET1V-0.413疏水扩容器坑排污泵DRAINFLASHTANKPITWASTEWATERPUMPSET2V-3.814#1低压加热器疏水泵LPlHEATERDRAINPUMPSET1vo.o15#2低压加热器疏水泵LP2HEATERDRAINPUMPSET1vo.o3.0主要工作量Mainworkquantity3.
10、1 设备开箱检验Unpackinginspectionequipment.3.2 设备吊装Liftingandhandlingequipment.3.3 就位设备的二次灌浆Alignmentandsecondarygroutingequipment.3.4 附件安装Attachmentinstallation.4.1 作业条件Workcondition4.1 技术资料准备Preparetechnicaldocuments4.1.1 厂家图纸、技术资料及安装图纸齐全。Manufacturerdrawings,technicaldocumentsandinstallationdrawingsare
11、complete.4.1.2 施工图纸审核完,施工现场备有安装图纸。Constructiondrawingsshouldbereviewed,andinstallationdrawingsshouldbeavailableatsite.4.1.3 安装基础尺寸与设备安装尺寸校验完。提交土建交付安装资料,包括记录图。Foundationdimensionsandequipmentinstallationdimensionsshouldbechecked.Submitdocumentsthatthecivilunithandsovertoinstallationunit,includingreco
12、rdchart.4.1.4 施工用料准备齐全。Materialsforconstructionshouldbereadyandcomplete.4.1.5 设备开箱清点已开始,并满足安装进度。安装前应逐一见证设备。Equipmentreceivinginspectionhasstartedandwhichmeettheinstallationschedule.Youshouldwitnessthedeviceindividuallybeforeinstalling.Certificatesshallbesubjecttoreviewtogetherbeforeinstalling.4.1.6
13、设备自带吊耳在应用前应进行检查。Liftinglugssuppliedwithdevicesshouldbeinspectedbeforetheyareused.4.1.7 参加施工人员必须熟悉施工图纸和设备安装工艺及标准。Constructionworkerswhoparticipateintheconstructionmustbefamiliarwiththeconstructiondrawings,equipmentinstallationtechnologyandstandards.4.2 作业人员配置Manpowerconfiguration职位Name单位Unit数量Quantit
14、y职位Name单位Unit数量Quantity施工负责人ConstructiondirectorPerson1起重工SignalmanPerson1技术员TechnicianPerson1钳工FitterPerson3管工PipefitterPerson1孟籍力工bangladeshlaboursPerson164.3作业工器具准备Toolsandinstrumentsforconstruction名称Name规格Specification数量Quantity名称Name规格Specification数量Quantity50t吊车50tcraneIset钢丝绳Wirerope32.54pcs汽
15、机房桥式起重机GTrommbridgecrane.9020tIset梅花扳手Boxwrenches2sets撬棍Prybar4pcs水准仪SpiritlevelIpc双头呆扳手Double-headedopen-endedwrenches2sets焊机及附件WelderandaccessoriesIpc水平尺RulerIpc榔头Hammer2.5pound2pcs平板车Platetrailer30tIset套筒扳手Socketspanner2sets套筒扳手Socketspanner2sets角磨机Anglegrinder1006pcs4.4安全设施准备Safetyfacilities名称Na
16、me数量Quantity名称Name数量Quantity安全网Securitynet40m2脚手架子管Scaffoldtubes60pcs安全警示牌Safetywaringboards6pcs跳板Springboard20pcs4.5其他准备Others4.5.1 基础交付使用,强度满足使用要求。Foundationhasbeenhandedovertoinstallationunitandfoundationstrengthcanmeetrequirementsforuse.4.5.2 安装设备验收合格。设备上的吊耳检查完好。Equipmentcanpassthroughinspection
17、.Liftinglugsontheequipmentisintact.4.5.3 各机械器具检查完确认无异常情况。Allmachineriesandtoolshavebeencheckedandconfirmednoabnonnalsituation.4.5.4 施工电源己接好,施工现场采光良好。Constructionpowersupplyhasbeenconnectedwell,andlightingisgoodonconstructionsite.4.5.5 施工人员到位,经过安全技术交底,并对施工任务及程序清楚明了。Constructionpersonnelarriveatsite,p
18、articipateinsafetytechnicaldisclosure,andknowconstructiontasksandprocedureswell.4.5.6 施工场地应平整无杂物,保持整洁。施工道路畅通,不得乱堆乱放,随意堵塞交通要道。Constructionsiteshouldbeflatandcleanwithoutsundries.Constructionroadshouldbesmooth,nostacking,itisnotallowedtoblockroadrandomly.4.5.7 氧气、乙焕、空气管道等力能供应已具备施工条件,且铺设整齐,符合安全作业要求,消防设
19、施齐全Oxygen,acetyleneandcompressedairpipelinesandothersupplycanmeettheconstructionconditions.Theyarenormallyarrangedinlinewiththesafetyandcivilizedconstructionoperationsrequirements.Fire-fightingequipmentisfullyequipped.5.1 作业方案Workscheme5.2 作业过程Theconstructionprocess5.2.1 施工准备T基础尺寸检查T设备搬运T设备吊装就位一附件安装
20、ConstructionpreparationBasesizechecktEquipmenthaulingEquipmenthoistinginpositionAttachmentinstallation.5.2.2 设备就位时采用滑移法,在设备底部铺设轨道后,通过轨道将设备滑至基础上。Theequipmentinplacebyslidemethodinplace,atthebottomofthedevicewillslideafterlaying,pulledtotheequipmentonthebasisof.5.3 施工步骤Constructionsteps5.3.1 基础验收Found
21、ationinspection检查混凝土基础表面应平整,无裂纹、孔洞、蜂窝、麻面和露筋等缺陷。检查基础中心线及基准点,允许偏差小于2mm。核对预埋地脚螺栓的数量、规格、位置及标高,预埋地脚螺栓的中心偏差不大于2mm,标高偏差应在0+2mm之内,对预留孔洞与预埋件也需要检查验收,保证其大小、位置和水平度都符合要求。Checkconcretesurfaceoffoundation,whichshouldbeflat,withoutdefectssuchascracks,holes,honeycomb,pittedsurfaceandexposedrebar.Checkthefoundationce
22、nterlineanddatumpoint,allowabledeviationshouldbelessthan2mm.Checkthenumber,specification,positionandelevationoftheembeddedanchorbolts.Thecenterdeviationoftheembeddedanchorboltsisnotgreaterthan2mm,andtheelevationdeviationshouldbewithin0-+2mm.Thereservedholesandembeddedpartsshouldbecheckedtoensurethei
23、rsizes,positionsandlevelmeettherequirements.5.2.2基础面凿毛Foundationsurfacechippingtreatment按图纸要求,对需要二次灌浆的区域内,基础表面凿去浮浆层,露出混凝土坚硬表面层,注意不应将混凝土中钢筋暴露出来。在去除浮浆的同时,要确保凿毛后基础表面的平面度,不应出现局部凹坑。Inaccordancewiththerequirementsofthedrawings,theconcretefoundationsurfacethatneedssecondarygroutingareashouldbechippedtoremo
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 汽轮机辅助设备安装方案 中英文 汽轮机 辅助 设备 安装 方案 中英文