厂区给排水管网施工方案 (中英文).docx
《厂区给排水管网施工方案 (中英文).docx》由会员分享,可在线阅读,更多相关《厂区给排水管网施工方案 (中英文).docx(17页珍藏版)》请在三一办公上搜索。
1、厂区给排水管网施工方案(中英文)目录CONTENT1编制依据Reference12 工程概况及工程量EngineeringBriefandQuantity22.1 工程概况EngineeringBrief22.2 主要工程量23 施工前准备及作业进度Preparationandprogressofoperationbeforeconstruction53.1 技术准备Technicalpreparation53.2 作业人员准备Preparationofoperatingpersonnel63.3 主要施工机械及工器具准备Preparationofmainconstructionmachine
2、andinstrument.73.4 4作业材料及半成品要求OPERATINGMATERIALSANDREQUIREMENTOFSEMI-FINISHEDPRODUCT.84 .施工方法及主要技术措施Constructionmethodandmaintechnicalmeasures941施工工艺流程94.1 土方开挖Earthworkexcavation94.2 管道安装Pipinginstallation104.3 排水检查井的施工要求13Drainageinspectionwellsconstructionrequirements134.4 管道水压试验Pipelinehydrostat
3、icpressuretest144.5 管道回填Pipelinebackfill145 作业质量要求QUALIFIEDREQUIREMENT155.1 质量要求及质量保证措施Qualityrequirementandmeasures156安全要求和措施SAFEMEASURES157.文明施工CIVILIZEDCONSTRUCTION171编制依据Reference1.1 生活给水管道施工图纸(F09151S-S0501)WaterSupplyPipelineConstructionDrawingGO915IS-SO501)1.2 雨排水管道施工图纸(F09151S-S0503)RainDrai
4、nagePipelineConstructionDrawingfF09151S-S0503)1.3 服务水管道施工图纸(F09151S-S0502)CoalMineWaterSprayPipelineConstructionDrawingfF09151S-S0502)1.4消防水管道施工图纸(F09151S-S0803)FirefighterPipelineConstructionDrawing(Fl0221SS1302)1.5 深井水管道施工图纸(F10221S-S0405)WaterSupplyPipelineConstructionDrawing(FlO221SS0405)1.6 事故排
5、油管道施工图纸(F10221S-S0405)2 工程概况及工程量EngineeringBriefandQuantity3 .1工程概况EngineeringBrief工程名称:孟加拉国KHULNA330MW(200-300MW)联合循环(双燃料)电站项目循环水管道安装工程;建设单位为BangladeshPowerDevelopmentBoard(BPDB);电厂额定容量:单循环:233MW(燃气),220MW(燃油);联合循环:357MW(燃气),336MW(燃油)。总承包方为江苏永鼎泰富工程有限公司,设计单位为浙江省电力设计院,中国能建东北电力第三工程有限公司负责承建。Projectname
6、:BangladeshKHULN330MW(200300MW)combinedcycle(dualfuel)powerplantcirculatingwaterpipelineinstallationproject;constructionunitisBangladeshPowerDevelopmentBoard(BPDB);ratedcapacityofthepowerplant:singlecycle:233MW(gas),220MW(Fuel);combinedcycle:357MW(gas),336MW(fuel).ThegeneralcontractorisJiangsuYongdi
7、ngTaifuEngineeringCo.,Ltd.,thedesignunitisZhejiangElectricPowerDesignInstitute,andChinaNengjianNortheastPowerThirdEngineeringCo.,Ltd.isresponsiblefortheconstruction.2.2主要工程量(已到图纸工程量)Mainquantities(workamountofexistingdrawing)2.2.1雨排水管道工程量Quantitiesofdrainagepipeline高密度聚乙烯缠绕增强管DN1200高密度聚乙烯缠绕增强管DNllOO
8、122米100米高密度聚乙烯缠绕增强管DN900270米高密度聚乙烯缠绕增强管DN70070米高密度聚乙烯缠绕增强管DN600135米高密度聚乙烯缠绕增强管DN500195米高密度聚乙烯缠绕增强管DN400255米高密度聚乙烯缠绕增强管DN300350米UPVC加筋排水管DN225540米UPVC力口筋排水管DN150170米圆形检查井中IOOO40座圆形检查井中12509座圆形检查井中150012座矩形检查井口1400*l1004座矩形检查井口1500*11004座雨水口680X380118座矩形检查井2200*22002座Highdensitypolyethylenewindingrein
9、forcedtubeDN1200122metersHighdensitypolyethylenewoundreinforcedpipeDNllOO100metersHighdensitypolyethylenewoundreinforcedpipeDN900270metersHighdensitypolyethylenewoundreinforcedtubeDN70070metersHighdensitypolyethylenewoundreinforcedtubeDN600135metersHighdensitypolyethylenewoundreinforcedtubeDN500195m
10、etersHighdensitypolyethylenewoundreinforcedtubeDN400255metersHighdensitypolyethylenewoundreinforcedtubeDN300350metersUPVCreinforceddrainDN225540metersUPVCreinforceddrainDN150170metersRoundinspectionWells401000roundinspectionshaft91250150012roundinspectionWellsrectangular1400*HOOfourinspectionwell4re
11、ctangularinspectionWells1500*11002rectangularinspectionWells2200*22002Rainwateroutlet680380118seats2.2.2消防管道工程量Quantitiesoffirepipeline钢丝网骨架聚乙烯复合管De315X131140米钢丝网骨架聚乙烯复合管De225X10275米钢丝网骨架聚乙烯复合管Del60X9355米钢丝网骨架聚乙烯复合管DellOX7120米衬胶消防弹性座封闸阀DN3006台衬胶消防弹性座封闸阀DN2004台衬胶消防弹性座封闸阀DNl5025台室外消火栓DNl5024套Steelmesh
12、skeletonpolyethylenecompositepipeDE315131140metersSteelmeshskeletonpolyethylenecompositepipeDE22510275metersSteelmeshskeletonpolyethylenecompositepipeDE1609355metersSteelmeshskeletonpolyethylenecompositepipeDEl107120metersRubber1InedfireprotectionelasticseatsealinggatevalveDN3006Gel-IInedfireprotect
13、ionelasticseatsealinggatevalveDN2004setsRubberlinedfireprotectionelasticseatsealinggatevalveDN15025setsOutdoorfirehydrantDN15024sets2.2.3生活给水管道工程量Quantitiesofdomesticwaterpipeline给水用聚乙烯管材Del10*6.6435米给水用聚乙烯管材De63*4.7125米弹性座密封闸阀DNlO0,PNLO2套RVHXDN100,PNl.02unit弹性座密封闸阀DN50,PNl.0RVHXDN50,PNLO1unitsPolye
14、thylenepipeforwatersupplyDEl10*6.6435mPolyethylenepipeforwatersupplyDE63*4.7125mElasticseatsealinggatevalveDN100,PNl.02setsRVHXDN100,PNLO2unitElasticseatsealinggatevalveDN50,PNl.01setsRVHXDN50,PNl.01units2.2.4服务水管道工程量Quantitiesofcoalyardsprayingwaterpipeline给水用聚乙烯管材De500*29.7293米给水用聚乙烯管材De160*9. 523
15、0米给水用聚乙烯管材Del10*6. 6255米给水用聚乙烯管材De63*4.7145米PolyethylenepipeforwatersupplyDE500*29. 7 293 mPolyethylenepipeforwatersupplyDE160*9.5 230 metersPolyethylenePipeforwatersupplyDEllO* 6.6255mPolyethylenepipeforwatersupplyDE63* 4.7145 m2.2.5深井水管道工程量Quantitiesofcoalyardsprayingwaterpipeline给水用聚乙烯管材Del40*8.3
16、1180米Polyethylenepipe for water supply DE140 *8. 31180m2 .2. 6 事故排油管道工程量 Quantities of coal yard spraying water pipeline球墨铸铁管DN400160米 Ductile iron pipe DN400 160 meters球墨铸铁管DN30050米 DUCtile iron pipe DN300 50 meters球墨铸铁管DNloo55米 DUCtiIe iron pipe DNlOO 55 meters3 施工前准备及作业进度Preparation and progress
17、of operationbeforeconstruction3.1技术准备 Technical preparation组织施工技术人员和主要施工人员审核图纸,会同甲方、监理单位及设计单位进行图纸会审。制定施工方案;提出施工材料计划;做好开工前的技术培训和技术交底工作。Organizeconstruction technician and main construction workers to review drawings and joint hearing with contractor consultant and design institute. Make construction
18、plan, putforwardplan of construction material, make good preparation of technical training and technicaldisclosure.32作业人员准备Preparationofoperatingpersonnel3.2.1人力准备Preparationofmenpower水暖工(当地临时工)3060人焊工(当地临时工)510人Plumberdocalpeople)30-60Welder(localpeople)5-10组长(中国工人)10人班队长2人Groupleader(Chinesepeople
19、)10Classcaptain2测量人员1人技术员1人Surveyor1Technician1管理人员2人dminiStrativestaff23.2.2作业人员要求Therequirementofoperatingpersonnel3.2.2.1施工人员进厂,首先要进行安全意识教育,文明施工的标准化教育,质量创精品意识教育。提高施工人员的思想意识,做到人人心中有目标,事事有标准,产品有实物比较。Beforeworkersgoingtosite,theyshallstudysenseofsafety,standardeducationofcivilizedconstruction,senseo
20、fexcellencewithqualitytoimprovetheideologyofconstructionworkers,everyonehaveagoalinmindandstandardineachwork,comparingproductswithrealobject.Specialoperationspersonnelshallneedprofessionaltrainingandtheyneedpasstheexaminationbeforeconstruction.Operationspersonnelshallworkaccordingtodrawings,theycann
21、otalterdrawingatrandom.3.2.2.2特殊作业人员需经过专业培训,并且考试合格后,方可施工。3.2.2.3施工人员应严格按照施工图纸施工,不得随意更改图纸内容。3.2.2.4管道安装施工前,要求管沟土方施工完,施工技术准备完。Beforepipelayingconstruction,earthworkofpipedrainandtechnicianpreparationshallbefinished.3.2.2.5班长要清楚本班所承担的施工项目施工顺序、施工方法、施工工艺要求,施工人员主要掌握施工方法、施工工艺。Foremanshallhaveagoodideaofcon
22、structionsequence、constructionmethodtechnologicalrequirementsofconstructionproject,constructorsshallmainlyknowwellaboutconstructionmethodtechnologicalrequirements.3.2.2.6参加施工人员进入施工现场,必须戴好安全帽,严禁酒后进入施工现场作业。Constructorsshallwearsafetyhelmetbeforegoingtosite,itisforbiddentogotositeafterdrinking.3.2.2.7施
23、工人员不得在施工现场随意乱串,不得乱动本专业以外的机械、设备。Constructorscannotwalkaroundatwillandalsocannottouchmachineorequipmentexcepttheirown.3.2.2.8施工人员不得在沟底休息或停留,若在沟底进行施工作业时,沟顶必须设监护人员。Constructorscannotrestorstayatthebottomoftrench,whenconstructionatthebottomoftrench,thereshallbeaguardian.3.2.2.9所有施工人员施工前必须参加施工技术交底并签字。Allc
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 厂区给排水管网施工方案 中英文 厂区 排水 管网 施工 方案 中英文
链接地址:https://www.31ppt.com/p-4322201.html