采煤机毕业论文外文翻译.doc
《采煤机毕业论文外文翻译.doc》由会员分享,可在线阅读,更多相关《采煤机毕业论文外文翻译.doc(9页珍藏版)》请在三一办公上搜索。
1、英文原文Utilisation of Data Mining in Mining Industry:Improvement of the Shearer Loader Productivity in Underground MinesI. INTRODUCTIONThe longwall system is the heart of the coal mining process. It is considered to have a simple layout but requires stringent adherence to some basic features in the dev
2、elopment of the panel to make it work. Similarly, in order to produce the required business production volume, all critical equipments must operate to their required level of service according to the systems established operating mission profile. The integrated nature of production system demands th
3、at all units or sub-systems should function with acceptable level of reliability to achieve planned production. The highly productive underground longwall mining equipment is very expensive and it requires proper assessment of serviceability of each component for maintenance management. Shearer is u
4、sed for getting coal in a longwall face and its breakdown is catastrophic in financial terms. Therefore, its availability is a must for the economic sustainability of the project. If the shearer is not working efficiently, this may reduce the efficiency of the entire production system 1. In the case
5、 of the highly mechanised shearer loader, an annual coal production target of four million tons was established to achieve the annual revenue target. To achieve this level of productivity, the shearer is expected to operate at 40 weeks-operating year at 106 hours per week and allowing for only two l
6、ongwall moves in a year. This tight target seems to be unrealistic considering the currentincreasing failure rate of the overall system. This unreliable condition only holds true in the absence of correct and auditable strategic maintenance and reliability policy, management systems and procedures i
7、n place. In this industrial case a substantial amount of time is being put together to systematically extract the appropriate data and analyse a few factors. The factors include the cause of failure, current maintenance regime, maintenance system and procedures, quality of computerised equipment his
8、torical records, data management and analysis and human reliability. This is in order to identify gap and implement effective solutions to the shearers current reliabilityshortcomings.The goal of this study is to develop a procedure to optimize maintenance plan for the Shearer Loader that would mini
9、mize costly production losses and improve reliability. The program is to consider long-term plant operation (with possible equipment life extension) by continuing with processes that have provided excellent past performance, proceeding with existing maintenance improvement programs, and recommend ne
10、w cost effective maintenance task.This study aimed at achieving the following objectives to drive delivery of the end goal:1) To identify a cost-effective maintenance strategy by reviewing, rationalising and optimising existing maintenance task.2) Apply design methodology in order to increase the le
11、vel of service from its current performance; improve life cycle cost and reliability of the Shearer over its design mission life.3) To develop guidelines for operation and maintenance integration4) Identify effective means of recording and utilising meaningful reliability data for performance analys
12、is.5) Ensure plant equipment is maintained appropriately byconsidering its importance to safety, reliability, and availability.The study also highlighted the significance of risk based assessment methodology such as FMEA/FMECA, Planned Maintenance Optimisation (PMO). The practice and principles of r
13、eliability and maintainability modelling has proven to generate increased profitability among world leader in mining industry. This method was found useful as an effective planning and operational tool for automatic and highly complex mine production system while employing almost without redundancy
14、high cost critical equipment i.e.,the Shearer Loader. This is where Return on Investment (ROI) can be justified by longer MTBF before scheduled maintenance task could interfere 2-3. The period of this study, where data were mined and analysed, was February August 2010. Interestingly, a positive impr
15、ovement in performance of the shearer has been observed since the early implementation of the analysis findings.II. THE FUNCTION OF THE SHEARER LOADERThe shearer loader installed in the underground mining is a Double Ended Ranging Drum Shearer (DERDS) equipped with outboard ranging arms. It is desig
16、ned and manufactured to extract and load coal into the Armoured Face Conveyor which is also a critical integral part of the longwall mining system. The Shearer operates within a minimum seam range of 1.8 metres and a maximum of 3.0 metres with an undercut of not less than 150mm with a 1000mm web. Th
17、e Shearer is also capable of both Half Web and Bi-Directional cutting and loading the full seam section at rated capacity to achieve the production requirements up to 4.0 million tonnes from theLongwall, in a 40 week operating year, with a weekly average of 100,000 tonnes. This operating schedule al
18、lows for two Longwall moves per year. The Shearer Loader is expected to achieve the equipment availability of not less than 98% of any given month, when operated 5-days a week (106 hours per week). Figure 1 shows the major components of the shearer loader.III. RELIABILITY ISSUES AND RISK ASSESSMENT
19、METHODOLOGYThe shearer failed to meet the availability performance target within the period due to several preventable failure modes that causes business interruptions. A SWOT analysis that was conducted from the start of this study shows the following factors directly impacting the shearer performa
20、nce;1. Planning and scheduling done in ad-hoc basis2. Equipment hierarchy limited to high level and does not capture failure modes to its component and sub-system component3. Compliance to maintenance schedule is inconsistent4. Poor data utilisation5. Backlog not measured6. Work order package incomp
21、lete (SWMS, JSA, drawings, BOM,etc.)A reliability analysis and comprehensive Failure Mode Effect and Criticality (FMECA) were carried out to identify failure rates of individual critical maintainable items and failure modes. The outcome of this process concluded with chronic reappearance of the same
22、 failed maintainable items caused by the same failure modes and failure mechanism that is causing the loss of its function. A Pareto analysis was used to identify a list of problems, using criteria of highest total revenue loss, breakdown frequency, Mean Time Between Failures (MTBF) and Mean Time To
23、 Repair (MTTR) 4. Pareto analysis identifies trailing cable failure as a leading contributory to cause business interruption. The sub-causes of this failure include the physical damage which occur majority of time and minor recurrence cause by electrical protection device malfunctioning and electric
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 采煤机 毕业论文外文翻译 采煤 毕业论文 外文 翻译
链接地址:https://www.31ppt.com/p-4069392.html