毕业设计英文翻译使用电超声波技术检测变压器局部放电1.doc
《毕业设计英文翻译使用电超声波技术检测变压器局部放电1.doc》由会员分享,可在线阅读,更多相关《毕业设计英文翻译使用电超声波技术检测变压器局部放电1.doc(27页珍藏版)》请在三一办公上搜索。
1、 译 文原文题目:Transformer Partial Discharg Detection Using Electrical-Ultrasonic Technology 译文题目: 使用电超声波技术 检测变压器局部放电 学 院: 电子信息学院 专业班级: 电气工程及其自动化2009级7班 学生姓名: 李龙龙 学 号: 20903040702 Transformer Partial Discharge Detection UsingElectrical-Ultrasonic TechnologyWei Jiang, Fan Liu, Zhiyuan WangSichuan Electric
2、Power Research InstituteChengdu, ChinaAbstractPartial discharge (PD) is usually happened caused by flaw and deterioration of transformer insulation. It is the main reason of the accident of transformer and power system. Therefore, its necessary and important to detect the partial discharge of transf
3、ormer while operating and manufacturing. When PD of transformer internal insulation occurs, electromagnetic waves, sound waves and other signals are produced. According to supersonic signal, we can detect the location of PD. But this method can not test the number of charge. With electrical-ultrason
4、ic detection method, it is easy to locate PD and test the number of charge. In this paper, a method of electrical-ultrasonic detection is presented, which is based three-dimensional scatter point and ultrasonic hit to time. The method is effective to locate fault of transformer insulation. To valida
5、te the approach, a case is introduced.KeywordsPartial discharge; Electrical-supersonic detection method; Pulse current method; Power transformer. INTRODUCTIONPartial discharge is common on account of flaw and deterioration of insulation, especially in power transformer, and is the main reason of the
6、 accident of transformer and power system. Therefore, its necessary and important to detect the partial discharge of transformer while operating and manufacturing. When PD of transformer internal insulation happen, electromagnetic waves, sound waves and other signals are produced at the same time. T
7、hough detect the ultrasonic signal, we can locate the PD1-3. PD detection using ultrasonic signal can locate the discharge, but this method can not test the number of the discharge. Partial discharge test can effectively test the discharge, but can not accurate locate 4-6. If we use PD ultrasonic lo
8、cation and partial discharge test at the same time, the number and location of discharge can be tested. We call this method is electical-ultrasonic technology 7-10. A method of electical-ultrasonic detection is presented in this paper, which is based three-dimensional scatter point and supersonic hi
9、t to time. With a case, the accuracy of PD electical-ultrasonic detection method is demonstrated. TRANSFORMER PD ELECTICAL-ULTRASONIC DETECTION PRINCIPLEWhen partial discharge of transformer internal isolation occurs, the ultrasonic signal will form spherical wave and spread to the surrounding with
10、1400m / s speed in the transformer oil. As long as placed ultrasonic sensors on the outside of transformer tank wall, ultrasound produced by PD can receive. We can locate the discharge of by detecting ultrasonic signal. But it hard to test the number of the discharge only by ultrasonic signal. Parti
11、al discharge test based on pulse current method can not accurate locate discharge source, though it can effectively test the discharge. So, electrical-ultrasonic, that detect both ultrasonic signal and pulse current discharge, can realize to test the number and location of discharge. The detection p
12、rinciple in Figure 1.Fig.1 Transformer PD electical-ultrasonic detection principleA. Partial Discharge Ultrasonic LocationPD ultrasound location method is that placing ultrasonic sensors on a few points of the transformer tank shell, composed of acoustic array to measure the spread time or relative
13、time of each sensor, then according to the time to solve equations of PD source location.Fig.2 Transformer PD ultrasonic detection principleWe can see from Fig.2. Set the coordinate of discharge source location is P(x,y,z), the transformer length, width and height are m, n and h. there are six senso
14、rs on the transformer tank shell. Their coordinates are (0,), (,n,), (,0,), (m,), (,0), (,0). So, the straight-line distance from the six sensors to PD source are:(1)(2)(3)(4)(5)(6)Set, are the time difference between PD source to 、 and PD source to. Set v is the ultrasonic speed. Therefore(7)(8)(9)
15、(10)(11)We can determine the locations of,.when we set the sensors on transformer tank shell. The time difference of can be between ,and can be measure by Multi-channel oscilloscope. So, the location of PD source can be get by solve formula(1)(11). Because transformer internal structure is complex,
16、which is compound of different materials, such as oil, copper, silicon steel and so on. Ultrasound propagation path is not complete linear, but it is include some refraction. Because the frequency of ultrasound is very high, refraction is very small. Therefore, by ultrasound signal, we can accuratel
17、y detect the location of partial discharge. More sensors we use, more accurate location we get.B. Transformer Partical Didcharge Test(1) Test methodPartial discharge test using power supply of five times the frequency,250Hz, apply test voltage in the transformer lowvoltage winding. A detection imped
18、ance are connected to the final layer of tested casing insulating paper, then link to the PD test apparatus by data cable.To supplement the transformer capacitive current, some reactors are paralleled to the transformer low voltage side, where is applied test voltage. Before the test, a square wave,
19、 with 500pC charge, are injected into the high (medium) voltage final layer of tested casing insulating paper to calibrated the number of discharge. Setting PD test apparatus to adjust PD 100 meter gauge shows full-scale grid, which indicated 500pC discharge. Transformer PD test principle using puls
20、e current method is shown in Fig 3.Fig.3 Transformer PD test principle using pulse current method(2) Test voltageSet is the maximum operating voltage, is equal to and is equal to . Turn on power supply in less than . Up voltage to , maintained this voltage for 5 min, maintained it for 5 min, and vol
21、tage to to and maintained 24 min. Then down voltage to , maintained it at less for half hours and test the number of transformer PD. Further reduced this voltage to , and maintained it for 5min.Turn off power supply when it less than . In the entire period of test, partial discharge should be monito
22、red.(3) Test compensationTaking into account that the capacity of the frequency power supply unit and possible resonance, discharge-free reactors are used in the test to compensate capacitive current. According to the actual power capacity, the required reactive power compensation can be estimated b
23、y the following formula:(12)Using the reactors to compensate for capacitive currents. During the voltage up to 20% and 50% , monitor compensation reactor and transformer current, and determine to increase or decrease the capacity of compensation reactor. EXAMPLE OF ELECTICAL-ULTRASONIC PD DETECTIONA
24、cetylene in oil of a 220kV substation #1 power transformer is excessive. Follow-up examination found that acetylene is still excessive, and there is a trend to further increase. Inner insulation of the transformer is likely to exist the phenomenon of partial discharge. To prevent transformer failure
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 毕业设计 英文翻译 使用 超声波 技术 检测 变压器 局部 放电
链接地址:https://www.31ppt.com/p-3975716.html