提升系统和安全装置毕业论文外文翻译.doc
《提升系统和安全装置毕业论文外文翻译.doc》由会员分享,可在线阅读,更多相关《提升系统和安全装置毕业论文外文翻译.doc(13页珍藏版)》请在三一办公上搜索。
1、英语原文Hoisting System And Safety DevicesThomas D.BarkandSenior Member,IEEEMine Safety And Health AdministrationPittsburgh,Pennsylvania 15236Abstract As noted,there are two main operating malfunctions which can occur in a hoist system that can kill men and damage equipment. 1. Overtravel at the shaft e
2、xtremity.2.Overspeed during the duty cycle .What is required in the case just illustrated is a device that would check hoist speed far enough down the shaft so that if the conveyance were traveling too fast at that point,the hoist would “E”stop soon enough to bring the skip to a stop before it overt
3、raveled its stopping point and did damage.This paper discusses the application of a suspension rope brake to a single rope mine hoist. Technical challenges associated with accelerated rope brake lining wear and suspension rope lubrication are addressed.HOISTING SYSTEMThe hoist together with its asso
4、ciated plant for an underground mine is the single most important and expensive lement of the mine plant.The hoist plant consists of all those components of mine plant that are necessary to elevate ore,coal,stone,or waste and to raise and lower personnel and materiel in the mine.It is with the hoist
5、ing system itself-these components of the hoist plant located in the hoist room-that engineering design is mainly needed.These key factors govern hoist selection:1. Production rate,or tonnage to be hoisted per unit of time2. Depth of shaft3. Number of levels to be accessedThere are basically only tw
6、o hoisting methods,plus some modifications,in use today:drum and friction.The drum hoist stores the rope not extended in the shaft.The friction-sheave hoist passes the rope (or the ropes) over the drive wheel but does not store it.A minor method that has fallen into disuse is reel hoisting,in which
7、a single width of rope is wrapped in many layers.A new method devised in South Africa for very deep shafts is multidrum hoisting using multiple ropes.DESIGN OF HOISTING SYSTEMThe design process for a mine hotsting stytem should be understood by the mining engineer,enen though the design and installa
8、tion are contracted to an engineer-constructor firm and the equipment bid to a hoist manufacturer.Typically,the mining company developing the mine assigns its own engineering department to monitor the entire process,including both the planning and construction of the surface hoist plant.The design p
9、rocess will now be examined in detail and illustrated by a numerial example.1. Balanced hoisting.All mine hoisting systems are operated in balance to reduce moments,torque,and power demand on the hoist.Generally,two conveyances are suspended from one hoist;sometimes,when more than one level is to be
10、 serviced,a counterweight replaces one conveyance.It is designed with a weight equal to the dead load ot the skip or cage plus one half the live load.To further balance the loads,a tail rope can be installed.2. Slippage in friction sheave hoisting.Slippage occurs in a friction-sheave hoist if the ra
11、tio of the rope tensions exteeds a theoretical limit.3. Wire rope size.Wire rope has a complex structure.In designing a hoisting system,the two properties of wire rope that are most important are weight per unit length and breaking strength.Note that properties for two qualities of steel are include
12、d for round-strand and flattened-strand rope.4. Sheave and drum diameter.To minimize flexing and stressing of the wire rope as it is wound over a sheave or drum,a recommended minimum ratio of drum or sheave diameter to rope diameter should be 80100.Since the cost of wire rope is modest,there may be
13、occasions,espcially in shallow shafts,where it is more coat-effective to select a smaller drum diameter and replace the hoist rope oftener.5. Rope fleet angle.This is the angle subtended by the hoist rope and the centerline from the idler sheave to the drum.To reduce rope abrasion in the sheave groo
14、ve,the fleet angle is restricted to 11.5.The principal effect of such a limit is to restrict the width of the drum.6. Skip size vs.hoisting velocity.To achieve a desired production rate in a shaft,the design engineer seeks a balance between skip size and hoisting velocity.The ultimate limit on skip
15、size is rope strength,and on hoisting velocity it is energy consumption.As a compromise it is generally advantageous to hoist the large skip load possible at the lowest possible rope velocity.7. Hoisting cycle.The relationship of time to distance in hoisting is referred to as the hoisting cycle.Calc
16、ulation of time and distance elements is accomplished with the following formulas:a. Acceleration time b. Acceleration distance c. Constant-velocity distance d. Constant-velocity time e. Cycle time 8. Duty cycle.The relationship between hoist motor torque requirements and hoisting cycle times is cal
17、led the duty cycle.The sloping section of the drum hoist reflects the unbalanced load of the hoist rope.Integrating the area under the curve provides the energy consumption for the hoisting-duty cycles.Safety Devices-like all mechanical devices with large heavy moving parts,such as gears,drums,conve
18、yances and motors,a mine hoist must bu protected from traveling too far in any given direction and traveling too fast.Protective devices are incorporated into a mine hoist for two reasons.The first is to protect life and limb of persons riding the cage and working in the vicinity of the shaft.The se
19、cond is to protect the hoist headframe and,most important,the shaft.As noted,there are two main operating malfunctions which can occur in a hoist system that can kill men and damage equipment.These are:1. Overtravel at the shaft extremity.2. Overspeed during the duty cycle.Overtravel is defined as t
20、ravel of a conveyance past the planned or programmed stopping point.This stopping point can be the dump bin in the headframe or a shaft loading pocket or cage landing. Overspeed is defined as speed in excess of that required or programmed for any particular point in the travel in the shaft.It can ea
21、sily be seen why this is important by considering the case when the skip is traveling at full speed while entering the dump scrolls. Given:Travel distance in dump scrolls 20ft(6.1m) Full hoist speed 30fps(9.14m/s) Emergency-stop retard rate 7.5(2.3m/) This means that the skip would overshoot the dum
22、p bin by some 60 ft.In all likelihood it would be pulled though the top of the headframe and thus damage structural work at the shaft collar.What is required in the case just illustrated is a device that would check hoist speed far enough down the shaft so that if the conveyance were traveling too f
23、ast at that point,the hoist would “E”stop soon enough to bring the skip to a stop before it overtraveled its stopping point and did damage.There are a mumber of such devices available around the world that,when geared and driven from the hoist drum(or wheel),will provide accurate and sensitive prote
24、ction of the hoist and conveyance from damage due to overtravel and overspeed.The best known and most widely used is the “Lilly Controller”,manufactured by the Logan Actuator Co.,Inc.,Chicago.INTRODUCTIONMine elevators and personnel hoists provide a lifeline for miners at more than 360 mines nationw
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 提升系统和安全装置 毕业论文外文翻译 提升 系统 安全装置 毕业论文 外文 翻译
链接地址:https://www.31ppt.com/p-3943940.html