砂石褥垫层夯填度施工记录表.doc
《砂石褥垫层夯填度施工记录表.doc》由会员分享,可在线阅读,更多相关《砂石褥垫层夯填度施工记录表.doc(23页珍藏版)》请在三一办公上搜索。
1、砂石褥垫层夯填度施工记录表 工程名称:龙韵华庭2#楼 时间:2014.11.17 (第一步)点位夯实前厚度(mm)夯实后厚度(mm)夯填度点位夯实前厚度(mm)夯实后厚度(mm)夯填度1-12011650.8212-12031650.8131-22031660.8182-22021640.8121-32001620.8102-32051660.8101-42011630.8112-42061660.8061-51991620.8142-52041630.7991-61981550.7832-62031620.7981-72031630.8032-72011620.8061-82011610.8
2、012-82001600.8001-92021620.8022-92031620.7981-102001610.8052-102051640.8001-111991600.8042-112011600.7961-121971600.8122-121991600.8041-131981620.8182-131981600.8081-141971610.8172-141961580.8061-152011600.7962-151951550.7951-162021620.8022-161941520.7841-172051660.8102-171961580.8061-182041650.8092
3、-181981580.7981-192031630.8032-191991590.7991-202011610.8012-201981600.8081-212001610.8052-211971570.7971-221981600.8082-221951550.7951-231971590.8072-231981590.8031-241951580.8102-242021600.7921-251961580.8062-252031610.7931-261991600.8042-262051640.8001-272011610.8012-272041610.7891-282001600.8002
4、-282061660.806 备注:图纸设计夯填度0.9,施工中由各楼施工员用水准仪测量,夯填前,每个控制点控制范围不大于9m2,用白石灰做标记,夯实后再用水准仪测量,使用机械为压路机(18t)、立式打夯机。压实遍数为四遍。施工员: 质检员: 监理单位(盖章):砂石褥垫层夯填度施工记录表 工程名称:龙韵华庭2#楼 时间:2014.11.17 (第一步)点位夯实前厚度(mm)夯实后厚度(mm)夯填度点位夯实前厚度(mm)夯实后厚度(mm)夯填度3-12001650.8254-12011610.8013-22011660.8264-22031630.8033-32001620.8104-32021
5、620.8023-41991600.8044-42041630.7993-51981600.8084-52011620.8063-62001600.8004-61981550.7833-72031630.8034-71991600.8043-82051640.8004-81971590.8073-92011620.8064-91971590.8073-102031610.7934-102011610.8013-112041600.7844-112021610.7973-122061650.8014-121991600.8043-132051650.8054-131981600.8083-142
6、031610.7934-142031610.7933-152041640.8044-152041620.7943-161991620.8144-162051630.7953-171981660.8384-172031620.7983-181991650.8294-182011610.8013-192011630.8114-192021630.8073-202021610.7974-202041630.7993-212031610.7934-212011610.8013-221991600.8044-221991600.8043-231971590.8074-231951590.8153-241
7、951580.8104-241981580.7983-252031580.7784-251971580.8023-262021600.7924-261981600.8083-272041610.7894-271961580.8063-282021600.7924-281991600.804 备注:图纸设计夯填度0.9,施工中由各楼施工员用水准仪测量,夯填前,每个控制点控制范围不大于9m2,用白石灰做标记,夯实后再用水准仪测量,使用机械为压路机(18t)、立式打夯机。压实遍数为四遍。施工员: 质检员: 监理单位(盖章):砂石褥垫层夯填度施工记录表 工程名称:龙韵华庭2#楼 时间:2014.11.
8、17 (第一步) 点位夯实前厚度(mm)夯实后厚度(mm)夯填度点位夯实前厚度(mm)夯实后厚度(mm)夯填度5-11991650.8296-12011650.8215-21981610.8136-22021660.8225-31951640.8416-32021620.8025-41981620.8186-42001660.8305-52001660.8036-52011620.8065-62031650.8136-61991600.8045-72011630.8116-71981600.8085-82021610.7976-81961600.8165-92051610.7856-91951
9、630.8365-102031600.7886-101941640.8455-112011590.7916-111951620.8315-121981580.7986-121961610.8215-131991620.8146-131981600.8085-141971610.8176-141991650.8295-151961660.8476-152021650.8175-161951620.8316-162011660.8265-172001600.8006-172031620.7985-182001600.8006-182041600.7845-192011600.7966-192051
10、630.7955-202031630.8036-202031610.7935-212011640.8166-212011610.8015-221991620.8146-222001610.8055-232011610.8016-232001600.8005-242001600.8006-242011590.7915-251981650.8336-252011580.7865-261981650.8336-262051580.7715-271981660.8386-272041600.7845-281991620.8146-282031580.778 备注:图纸设计夯填度0.9,施工中由各楼施工
11、员用水准仪测量,夯填前,每个控制点控制范围不大于9m2,用白石灰做标记,夯实后再用水准仪测量,使用机械为压路机(18t)、立式打夯机。压实遍数为四遍。施工员: 质检员: 监理单位(盖章):砂石褥垫层夯填度施工记录表 工程名称:龙韵华庭2#楼 时间:2014.11.17 (第一步)点位夯实前厚度(mm)夯实后厚度(mm)夯填度点位夯实前厚度(mm)夯实后厚度(mm)夯填度7-12001610.8058-12031650.8137-22031600.7888-22011660.8267-32011590.7918-32001620.8107-42021580.7828-42051630.7957-
12、51991580.7948-52041620.7947-61981600.8088-62061550.7527-71951580.8108-72031630.8037-81961600.8168-82041610.7897-91981600.8088-92021620.8027-101971630.8278-101991610.8097-112011640.8168-111981600.8087-122021620.8028-121981600.8087-131991610.8098-131961620.8277-141991600.8048-141981660.8387-152011650.
13、8218-151991620.8147-162031650.8138-162021600.7927-172001660.8308-172011600.7967-181991620.8148-182031600.7887-191961600.8168-192001630.8157-201951610.8268-202001640.8207-211961610.8218-212011620.8067-221991610.8098-222031610.7937-232011600.7968-232021600.7927-242031590.7838-241991650.8297-252001580.
14、7908-251981650.8337-262021580.7828-261991660.8347-272041600.7848-272001620.8107-282051580.7718-282001600.800 备注:图纸设计夯填度0.9,施工中由各楼施工员用水准仪测量,夯填前,每个控制点控制范围不大于9m2,用白石灰做标记,夯实后再用水准仪测量,使用机械为压路机(18t)、立式打夯机。压实遍数为四遍。施工员: 质检员: 监理单位(盖章):砂石褥垫层夯填度施工记录表 工程名称:龙韵华庭2#楼 时间:2014.11.18 (第二步) 点位夯实前厚度(mm)夯实后厚度(mm)夯填度点位夯实前
15、厚度(mm)夯实后厚度(mm)夯填度1-12011650.8212-12031650.8131-22031660.8182-22021640.8121-32001620.8102-32051660.8101-42011630.8112-42061660.8061-51991620.8142-52041630.7991-61981550.7832-62031620.7981-72031630.8032-72011620.8061-82011610.8012-82001600.8001-92021620.8022-92031620.7981-102001610.8052-102051640.800
16、1-111991600.8042-112011600.7961-121971600.8122-121991600.8041-131981620.8182-131981600.8081-141971610.8172-141961580.8061-152011600.7962-151951550.7951-162021620.8022-161941520.7841-172051660.8102-171961580.8061-182041650.8092-181981580.7981-192031630.8032-191991590.7991-202011610.8012-201981600.808
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 砂石 褥垫 层夯填度 施工 记录

链接地址:https://www.31ppt.com/p-3920762.html