1、PMP认证考前模拟试题声明:以下试题是PMP考试的相同类型题。本试题仅为复习目的。通过这份试题不意味着通过PMP认证考试。1.One of the main advantages of a matrix organization is:A.Improved project manager control over resources B.More than one boss for project teamsC.Communication is easierD.Reporting is easier矩阵组织的一个主要优点是:A项目经理可以更好地控制资源。B项目团队可以有多个老板。C沟通更便捷。
2、D报告更容易。2.A detailed project schedule can be created only after?A.A project plan is created.B.A WBS is created. C.A budget is created.D.A project control plan is created.详尽的项目进度计划只能在_后创建?A创建好项目计划B创建好工作分解结构C创建好预算后D创建好项目控制计划3.In what organization project member feel most anxiety at closing phase?A.Func
3、tionalB.MatrixC.Projectized D.Strong Matrix在哪种组织中,项目成员在项目收尾阶段最为焦虑?A职能型B矩阵C项目型D强矩阵4.A project managers company operates in a high-technology area requiring the integration and sharing of several functional specialties. The project manager is considering the appropriate organizational structure for a
4、new project. The likely choice would be-A.Matrix B.Tight matrixC.FunctionalD.Projectized项目经理所在的公司从事高科技领域,需要综合并共享几个职能特性。项目经理现正为一个新项目选择合适的组织结构。以下哪项选择可能适合?A矩阵B强矩阵C职能型D项目型5.What is the document that forms the basis for an agreement between the project team and the project customer by identifying both th
5、e project objectives and the major project deliverables?A.Implementation PlanB.Configuration Management PlanC.Scope Statement D.Work Authorization Plan有一个文件,它通过确定项目目标和主要项目可交付成果,形成了项目团队和项目客户之间达成一致的基础。这个文件的名称是?A执行计划B配置管理计划C范围说明书D工作授权计划6.The project charter is created during which life cycle phase?A.Pl
6、anningB.Feasibility studyC. ExecutionD. Initiation项目章程是在哪个项目生命阶段产生的?A计划编制B可行性研究C执行D启动7.The scope of a project is fully described by:A.the request for proposal B.the statement of workC. a five level project work breakdown structureD. the sum of the products and services delivered项目范围由什么充分说明?A建议书邀请函B工
7、作说明书C5级工作分解结构D交付产品和服务的总和8.Each item of the Work Breakdown Structure is assigned a unique identifier. What is the name of this identifier?A.Quality inspection identifier.B.Chart of accountsC.Project activity codeD. Code of accounts 工作分解结构中的每一项都被标以一个独特的标示符。标示符的名称是什么?A质量检测标示符B帐目图表C项目活动编码D帐目编码9.A WBS nu
8、mbering system should allow project staff to:A.Estimate costs of WBS elementsB.Provide project justificationC.Identify the level at which individual WBS elements are found D. Use it in project management software工作分解结构编号系统允许项目员工:A估算WBS元素的成本B提供项目论证C确定在哪个级别可以找到WBS元素D在项目管理软件中使用编码系统10.Scope verification
9、 should be done?A.At the end of the projectB.At the beginning of the projectC.During each phase of the project D. Once during planning范围核实应该在何时进行?A项目结束时B项目开始时C项目每一个阶段期间D计划编制时进行一次11.In order to manage a project effectively, work should be broken down into small pieces. Which of the following does NOT
10、 describe how far each task should be broken down?A.Can be completed in under 80 hoursB.Can not be logically subdivided furtherC.Is done by one person D. Can be realistically estimated为了有效的管理项目,应该将工作分解为小块。以下各项中哪项不能说明任务应该分解到什么程度?A可以在80小时以下完成。B不能再进一步进行逻辑细分了。C可由一个人完成。D可以进行实际估算。12.Customer is requiring
11、scope changes. In order to analyze the influences to the project, PM should review WBS, change request, scope management plan and A.Performance Report B.RAMC.Pareto DiagramD.Monte Calro Simulation客户要求进行范围变更。为了分析变更对项目的影响,项目经理应该回顾工作分解结构、变更请求、范围管理计划和_?A绩效报告B职责分配矩阵C帕累托图D蒙特卡洛模拟13.A project manager may us
12、e to make sure the team clearly knows what work is included in each of their tasks?A.A project scope of workB.A project charterC.A WBS dictionary D.A risk management plan项目经理可以使用_来保证项目团队清楚的了解到他们的每一项任务包含的工作。A项目工作范围B项目章程CWBS词典D风险管理计划14.The WBS is an input to scope change control because it-A.Provides
13、information on project objectivesB.Defines the projects scope baseline C.Defines all project baselinesD.Provides information on scope performance工作分解结构是范围变更控制的一个输入,因为它:A为项目目标提供信息B定义了项目的范围基准计划C定义所有项目基准计划D为执行范围提供信息15. The scope of a project can be expected to change during the project life cycle. The
14、document that describes how the project scope changes will be integrated into the project is the:WBS dictionaryScope statementScope management planProject Charter在项目生命周期内,可能想要变更项目范围。表述项目范围的变更怎样整合到项目之中的文件是:A. 工作分解结构WBS字典B. 范围说明书C. 范围管理计划D. 项目章程16. Project managers normally manage to the third level o
15、f the WBS. Managing at this level allows the project manager to:Supervise all technical workControl the work package elementsExercise his or her technical expertiseMaintain better control of integrated efforts项目经理通常管理工作分解结构WBS的第3级,该水平的管理让项目经理去:A. 监督所有技术工作B. 控制工作模块要素C. 发挥自己的技术专长D. 更好地保持控制整合工作17. You
16、have been assigned as a project leader and must first review the statement of work provided by the customer. Although the answer can vary based on the industry, choose which one of the following are you most likely to overlook?Data item deliverablesCustomer-furnished equipment and facilitiesLong-lea
17、d procurement itemsCustomer-imposed milestones你被安排负责项目,首先必须检查评审客户提供的工作说明书。尽管不同的产业会有不同的答案,你最可能忽视下列哪项:A. 工作成果数字化B. 客户提供的设施C. 长期重要的采购内容D. 客户要求的工作里程碑18. To further ensure that the work outputs of the project are accepted by the customer, the project team should:Change the project scope when requested by
18、 the customerFollow a scope verification processModify the project plan and baseline as needed.Use a PERT Chart为了进一步确保客户接受项目的工作结果,项目团队应该:A. 当客户要求时,变更项目范围B. 遵循范围确证过程C. 根据需要调整项目计划和基准D. 利用计划评审技术PERT图19. Scope changes on projects are inevitable. However, scope changes can be minimized by:Effective imple
19、mentation of the scope management processesSpending more time analyzing where the estimates came from and who did the estimatingAsking the sponsor to supervise all of the planningDeveloping a detailed Project Charter项目范围变更在所难免。然而,要尽可能减少范围变更可以借助于:A. 有效完成范围管理过程B. 花更多时间分析估算是怎样得出的及是谁做估算C. 请求业主监督规划的所有事项D
20、. 制定详尽的项目章程20. A company convenes an estimating team to bid competitively on a project. Later, a negotiation team made up of different people is established to negotiate the final price. The project manager was not part of either team and is assigned after negotiations were completed and the contrac
21、t was signed. A good project manager should mainly:Disregard the assumptions/constraints used in estimating the jobReview the documents that authorize the project and define its objectivesFocus heavily on comparing the contractual statement of work with the proposal statement of workRequest a new pr
22、oject charter某公司召集一个估算团队来对项目竞标报价。稍后,由不同的人组建了一个谈判团队来谈判决定最终价格。在完成了谈判并签订了合同后,才任命了项目经理,他并不是上述两个团队的成员。一个好的项目经理应该主要:A. 不考虑工作估算所作的假定或条件限制B. 了解检查项目授权和项目目标的文件.C. 集中精力比较工作的合同要求说明书和工作建议说明书D. 要求制定新的项目章程21. A project charter is a document issued by a that provides the project manager with the authority to apply
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 非常经典,打灯笼都找不到的好资料 PMP 认证 考前 模拟 试题 非常 经典 灯笼 找不到 资料
链接地址:https://www.31ppt.com/p-3818014.html