APQP项目启动会议表格.doc
《APQP项目启动会议表格.doc》由会员分享,可在线阅读,更多相关《APQP项目启动会议表格.doc(6页珍藏版)》请在三一办公上搜索。
1、Date日期2013-10-24Project项目CD8105/71&CD7105/71Part No.产品编号3140 170 51441Supplier供应商ALPSPart Description产品描述BT Module UGZZCManufacturing Location制造地点SQM to confirm manufacturing location is the same as stated on the supplier RFQ response and Desay SV contractSQM需要确认供应商的制造地点是否与当初报价或签署合同上的地点一致Prior to th
2、e Kick Off Meeting supplier should ensure full understanding of the APQP Project Plan and all related procedures. Any issue requiring clarification needs to be addressed to SV SQM.在启动会议之前,供应商应确保完全理解APQP项目计划和相关程序,任何问题需要澄清,请联系德赛西威SQM工程师。Section 1. Customer Requirements - All unresolved items must be a
3、dded to Open Issues List 第一部分 客户要求-所有未解决的事项必须增加到问题开放清单中1. Does the supplier have and understand the latest information about project timing (e.g. Prototype, GFT, B1 Sample , B2 Sample, C Sample, D Sample, SOP)? Is the supplier familiar with the quality requirements by build level? 供应商是否有并且理解了最新的项目时间
4、信息(如模具启动时间,B1样件,B2样件,C样件,D样件,量产开始时间)?供应商是否熟悉各个阶段的样件质量要求? Yes NoExplain:与供应商评审项目里程碑Key Project Milestones关键项目里程碑Dates 日期A0样件45/13A1样件51/13B1样件19/13C0样件28/13C样件48/13D Sample D样件1/15SOP 量产开始时间20/152. Does the supplier have a clear understanding of the Desay SV standards? If “no”, the supplier shall rev
5、iew with the related Desay SV SQM person?供应商是否清晰理解德赛西威的标准?如果不,供应商应该和德赛西威的SQM工程师评审相关标准要求? Yes NoExplain:3. Is contact established between supplier and Desay SV supply chain? Review packaging or shipping open issues.供应商与德赛西威供应商链的联系窗口是否建立?评审包装或发运未关闭的问题。 Yes NoExplain:Connect WindowDesay SVALPSDept.Name
6、E-Mail PMHe ZhiliangZhiLiang.Hedesay-SQMYang ZunfengZunfeng.yangdesay-EEZhang ShunjunShunJun.Zhangdesay-SWSun SainanSaiNan.Sundesay-PPQiu LongwenLongwen.Qiudesay-SPSu Jianjian.sudesay-4. Does supplier understand that APQP performance is the part of the whole quality performance? For example quality
7、incidents.供应商是否理解APQP的表现是整个质量表现的一部分?例如质量事件。 Yes NoExplain: Section 2. Product Design & Development - All unresolved items must be added to Open Issues List第二部分 产品设计和开发-所有未解决的事项必须增加到问题开放清单中5. Does the supplier have and understand all of the latest drawings and specifications including GQA ,GQAS and a
8、ll Desay SV Standards (STD)?供应商是否有并且理解所有最新的图纸和规范包含通用质量协议,通用质量应用标准和所有德赛西威的标准? Yes NoExplain plans to obtain: GQAs详见附件6. Specify who is responsible for design, Desay SV or supplier. 明确指定谁负责产品设计,德赛西威或供应商? Desay SupplierComments:7. Has a design review been done by the supplier and reviewed with the Desa
9、y SV product engineer?供应商是否有做设计评审,并且与德赛西威的产品工程师进行了评审? Yes NoIf No, explain:If yes, have drawings/specifications been revised as appropriate? 如果是,图纸和规格书是否有适当的更新?Does design support good perceptual quality (i.e. how the customer see/ feel the part) 设计是否支持满意的质量期望(如客户对零件的感觉怎样)?Does the supplier understa
10、nd the critical nature of dimensions that interface with the customers application of their mating parts? Are there any matching requirements? 供应商是否理解零件的关键尺寸特性,该特性是匹配客户端其它零件的?是否有匹配的要求?For parts with matching requirements how will tooling design facilitate ease of matching changes对于有匹配要求的零件,模具设计怎样使匹配
11、变化容易受控? Yes NoSpecify plans 8. What Desay SV Lessons Learned does the supplier need to incorporate in the Product Design & Development? Desay SV SQM to facilitate by collating and providing lessons learned to supplier. Consider all sources for data including Problem list, and relevant databases.供应商是
12、否需要在产品设计和开发过程中考虑德赛西威的经验教训?德赛西威的SQM通过校对和提供经验教训来推动供应商,考虑所有数据来源包含问题清单及相关的数据库。Desay SV Lessons Learned德赛西威经验教训 Supplier Lessons Learned供应商经验教训供应商需提供BT模块推荐的过炉温度曲线蓝牙模块包装使用卷装提高生产效率每批次出货时在包装上体现软件版本信息9. Has an Analysis Development Validation Plan been provided if specified in the Requirements? Is the supplie
13、r aware of, and have a plan for, the testing under supplier responsibility? Does the supplier understand that the ADV is the base for signed ISTR (validation approval) for PPAP submission?分析开发验证计划是否有提供如果在要求里有明确说明?供应商是否有意识到供应商的设计职责必须有一个测试计划?供应商是否理解分析开发验证报告是签署ISTR的基础,ISTR是PPAP必须提交的内容? Yes NoSpecify:IS
14、TR的要求详见附件10. Has a Design-FMEA review been done between supplier and the Desay SV Engineer? Has an RPN reduction been developed ?供应商和德赛西威的工程师之间是否有进行DFMEA的评审?是否开发了一份风险降低的行动计划? Yes NoSpecify planned date:Section 3. Process Design & Development - All open issues recorded on the Open Issues Form.第三部分 过程
15、设计与开发-所有未关闭的事项需记录到开放问题清单中11. Does the supplier need to develop any new facility for production? If yes, how will facility readiness be tracked and progress reported to the Desay SV SQM.供应商需要开发新的工厂来生产吗?如果是,工厂准备状况的跟进和进展如何报告给德赛西威的SQM工程师? Yes No If Yes, explain plans. 12. Has the supplier confirmed thei
16、r responsibility for management of all tiered suppliers and subcontractors, including directed buy subcontractors? Desay SV SQE to review sub-contractor management plan including APQP, PPAP, Run Rate.供应商是否确认了他们管理下级供应商和转包商的职责,包含客供料的职责?德赛西威的SQM将会评审下级供应商或转包商的管理计划,包含APQP,PPAP和RR。 Yes NoExplain:13. What
17、Desay SV Lessons Learned does the supplier need to incorporate in the Process Design & Development? Desay SV SQM to facilitate by collating and providing lessons learned to supplier. Consider all sources for data including Problem list and relevant databases.供应商是否需要在过程设计和开发过程中考虑德赛西威的经验教训?德赛西威的SQM通过校
18、对和提供经验教训来推动供应商。考虑所有数据来源包含问题清单和相关数据库。Desay SV Lessons Learned 德赛西威经验教训Supplier Lessons Learned供应商经验教训14. What new equipment, tooling, gages, special fixtures or test equipment is needed to produce this part? Is supplier aware of, and will supplier comply with, Fixture Standard?需要哪些新设备,工模具,量具,特别夹具或测试设
19、备来生产该零件?供应商是否意识到夹检具需要符合夹检具标准? Yes NoComment15. Has error proofing been considered during preliminary PFMEA creation and included in quoted price? Has the supplier developed an RPN reduction plan for the Process FMEA. SQM to review the plan.供应商是否在初始的PFMEA中就考虑到了防错,并且这些防错都已经包含在报价中了?供应商是否对PFMEA开发了一份风险降低
20、计划?德赛西威的SQM将会评审这份计划。 Yes No If No, explain plans to achieve quality requirements 16. Desay SV minimum required acceptance criteria for the PPAP initial statistical study for KPC and PQC is established in the GQA. Are any print, material specifications or process control plan changes needed to meet t
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- APQP 项目 启动 会议 表格
![提示](https://www.31ppt.com/images/bang_tan.gif)
链接地址:https://www.31ppt.com/p-3802780.html