Waste Management Safe work instruction 安全工作指导 非洲矿业有限公司AML HSE安全管理制度 英文版.doc
《Waste Management Safe work instruction 安全工作指导 非洲矿业有限公司AML HSE安全管理制度 英文版.doc》由会员分享,可在线阅读,更多相关《Waste Management Safe work instruction 安全工作指导 非洲矿业有限公司AML HSE安全管理制度 英文版.doc(3页珍藏版)》请在三一办公上搜索。
1、SAFE WORK INSTRUCTIONWASTE MANAGEMENTDocument Custodian:Manager HSEDocument Checked:Document Approved:TABLE OF CONTENTS1.DISTRIBUTION22.SCOPE23.REFERENCE24.DEFINITIONS25.PROCEDURE25.1Waste Identification25.2Waste Reduction and Monitoring26.TABLE 1 WASTE MANAGEMENT TABLE37.APPENDICES/FORMS3SWI-F0450A
2、Waste Disposal RecordSWI-F0450BWaste Monitoring Checklist1. DISTRIBUTIONThere are no restrictions on the distribution of this procedure within the Company.2. SCOPEThis procedure details the practices used to ensure that waste generated as a result of construction and demolition activities is minimis
3、ed, recycled, reused or recovered.3. REFERENCENil4. DEFINITIONSNil5. PROCEDURE5.1 Waste IdentificationThe Construction Manager, in conjunction with the Project HSE Coordinator (PHSEC), shall identify the wastes likely to be generated by the project during construction. For each identified waste the
4、PHSEC and Construction Manager shall determine the necessary control measures required.Where the waste is to be recycled, the PHSEC shall contact the respective recycling organisation or the Environmental Officer to arrange for: storage containers to be situated on site for waste collection, the rem
5、oval of waste from site at nominated frequencies.Typical types of waste, control measures and frequency of monitoring are detailed in the waste management practices detailed in Table 1.All site works are to be undertaken in a manner that endeavours to minimise the amount of waste generated, and maxi
6、mise the opportunity to recycle or reuse waste products.The Construction Manager shall ensure that all site subcontractors are fully informed of their responsibilities and requirements with respect to minimising and managing waste on site. 5.2 Waste Reduction and MonitoringThe PHSEC, shall implement
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- Waste Management Safe work instruction 安全工作指导 非洲矿业有限公司AML HSE安全管理制度 英文版 安全

链接地址:https://www.31ppt.com/p-3025759.html