精益生产快速换模改善案例(经典作品) .ppt
《精益生产快速换模改善案例(经典作品) .ppt》由会员分享,可在线阅读,更多相关《精益生产快速换模改善案例(经典作品) .ppt(27页珍藏版)》请在三一办公上搜索。
1、ManzoniSMEDStamping Workshop,Apr,12th16th 2010,现场改善GK 129,1000T 快速换型,2,Presentations Title,GK129 team 改善团队 奔驰,Team members 团队成员冲压主任 龚小范维修主任张建强模修领班王佑春传播者 王伟操作工 张传有模修王树林维修计划刘景鹏电子工程师 刘伟东860项目组胡智平860项目组高洋巴西专家Silviu巴西专家Evandro Speckhahn巴西模修Renato精益 张春杰,3,Presentations Title,The source of the GK 项目来源,1.VS
2、M 价值流程图,2.860项目组 Capacity Expansion project 8.6 M/y,4,Presentations Title,Objective and Goal 目的与目标降低1000T换型时间=从35分钟至20分钟Decrease the setup model time(1000T)=From 35mins to 20 mins人因工程改善=1项 Ergonomic Improvement=1 Item安全改善=1项 Safety Improvement=1 Item可视化管理=1项 Visual Management=1 Item5S改善=1项 5S Improv
3、ement=1Item,Objectives and Goal 目的 与目标,5,Presentations Title,Benefits of SMED 快速换型的好处,Reduces unproductive time减少非生产时间,Allows to improve the client service(lead time,quantity)有利改善客户服务(交货周期、数量等),Enlarges real capacity of machines扩大机器实际产能,Reduce the investment and production cost减少投资,降低成本,SMED快速换型,All
4、ows to reduce the stocks有利降低库存,Shorter series becomes cheaper(reduce batch size)产品系列更换时间更短、成本更低(缩小批量),6,Presentations Title,Step 1 步骤一,Step 2 步骤二,Step 3 步骤三,Step 4 步骤四,Step 6,Changeover method not rationalised没有理顺换模方法,Study of the actual situation研究实际情况,Separate internal work From external work将内部工作
5、与外部工作分开,Convert internal work in external work将内部工作转化为外部工作,Step 5 步骤五,Reduce of internal work减少内部工作,Absence of method 没有方法,Preparation time with big variations 准备时间变化太大,There is no distinction between external work and internal work 内部和外部工作没有什么区别,Improvement of logistic support改善物流运输,Improvement ser
6、viceability改善可用性,Pre-assembly 预先装配,Pre-adjustments 预先调整,Pre-heating 预热,Previous work before the machine stop 停机前的准备工作,Work to be done with the machine stopped 停机时要做的工作,Work to be done after stopping 停机后要做的工作,Register and classified all the necessary working elements 将所有必要的工作进行登记和分类,Video 视频,Chronogr
7、aph 计时器,The 5 Steps of SMED 快速换型的五个步骤,SMED 快速换型,Eliminate adjustments and settings 消除调整和设定,Simplify fixation and tightening 简化固定和上紧程序,Parallel work 平行作业,Internal Work:Operations which have to happen when the machine is not running外部工作:机器没有运作时要进行的工作,External work:The operations which can take place w
8、hen the machine is running内部工作:机器运作时要进行的工作,Reduce of external work减少外部工作,7,Presentations Title,Step1:Study of the actual situation 步骤一:研究实际情况,Make the list of setup step through film观看录像列出换型步骤(共59步),8,Presentations Title,Step 2 Separate internal work From external work 步骤二:区分内部工作和外部工作,对59步换型步骤进行内部外部
9、工作的区分,9,Presentations Title,After Kaizen改善后,Before Kaizen改善前,Step 3 Convert internal work to external work 将内部工作转换成外部工作,工具准备 Prepare and Organize tools,Photo,将换型工具按照模型摆放在车上,便于取放。同时增加1个套筒和1个六角扳手Put the tools in the car according the former in order to take easily and at the same time add 1 steel tube
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 精益生产快速换模改善案例经典作品 生产 快速 改善 案例 经典作品
链接地址:https://www.31ppt.com/p-2911424.html