1、三江学院毕业设计(论文)外文资料翻译院 系土木工程专业建筑工程学生姓名许学斌班级学号 B08084066外文出处Knight M A, Mitchell R J. Modeling of light non-aqueous phase liquid (LNAPL) releases into unsaturated sand .Canadian Geotechnical Journal, 1996,33, 33 :913-925 . 附件:1.外文资料翻译译文(约3000汉字); 2.外文资料原文(与课题相关的1万印刷符号左右)。指导教师评语:指导教师签名:年月日Bored pileSumma
2、ry Drill ( flushing, dig ) pile from the nineteen sixties, beginning in Henan province Nanyang region since the development application, because of its many advantages, has been widely used in soft soil, loess, including soil, expansive soil and other special types of foundation and industrial, civi
3、l, municipal, railway, highway, port and other types of Engineering practice. And precast pile, bored pile construction of no noise, no vibration, on the surrounding buildings and small environmental impact, pile diameter, buried deep, large bearing capacity. Chinas drilling pile maximum diameter of
4、 pile has reached 4000mm, maximum deep pile has reached 104m, and the steel pipe pile maximum diameter of 1200mm, the largest pile of prestressed concrete pipe pile with deep 83m, maximum diameter of 1300mm, the biggest pile depth 40m. Along with our country socialist construction is booming, with h
5、igh-rise buildings, large span bridges on the rise, the bearing capacity of pile foundation with higher requirements. Large diameter bored pile therefore gets rapid development, pile length and pile diameter also do bigger more. However, in the existing various methods of pile, bored pile has many a
6、dvantages and is widely used in construction, but it is hard to avoid the impact of mud, which not only reduces the bearing capacity of pile expectations, but also caused a serious waste of materials. Manual hole digging pile is difficult to achieve greater depth, its bearing capacity is also diffic
7、ult to just as one wishes. In view of bored pile in this situation, how to improve the pile construction technology level, make the input material to be more reasonable to use, so as to greatly increase the bearing capacity of single pile in engineering field, have become hot issues in recent years.
8、The introduction of bored cast-in-place pile Perfusion pile refers to the construction site by mechanical drilling, steel pipe soil compaction or human mining method in the foundation pile hole in form, and on its inner placed reinforcement cage, concrete made with different pile, drilling method, g
9、routing pile can be divided again for cast-in-place pile, bored pile and digging several types of piles. Bored pile by pile into the definition and classification of a kind of pile.The characteristics of bored cast-in-place pile1、And sinking pile of hammering method, construction noise and vibration
10、 is smaller2、To construct than the precast pile of large diameter of pile3、In all kinds of ground can be used4、The construction quality of the pile bearing capacity influence5、Because the concrete is in the mud perfusion is difficult to control, so the quality of concreteBored pile construction meth
11、od Percussion drilling, punching grabbing drilling and rotary drilling hole can adopt slurry wall construction method. The construction process is: site formation, slurry preparation, buried tube and laying work platform rig and positioning, drilling, hole cleaning and inspection of hole quality and
12、 lower steel cage, underwater concrete perfusion to pull out the barrel to check quality. Construction sequence: (1) the construction preparation Construction preparation comprise: selecting drill, drill, layout. Construction of bored pile drilling rig is the main equipment, according to the geologi
13、cal conditions and various drilling machine applied to select conditions (2) drilling machine installation and positioning Istallation of drilling machine based if not stable, easy to produce in the drilling machine construction, pile and pile inclined inclined eccentric and other adverse effects, t
14、herefore requires the installation of foundation stability. On the formation of softer, sloping ground, be bulldozed, the pad plate or tie reinforcement. In order to prevent the pile position allowed, construction is very important to the set the center position and the correct installation of drill
15、ing machine, the rig drilling machine, first use of the power drill and near the cage with the drill pipe, moving roughly position, and then Jack rack jacking, accurate positioning, so that the lifting pulley, drill bit or fixed drill hole cards and casing center in a vertical line, in order to ensu
16、re the verticality of the drilling rig. Drilling position deviation is not more than 2cm. Aligned with the pile location, with sleeper flat drill beam at the top of the tower, and symmetrical to the drill axis pulling cable wind rope. (3) buried tube Underground water level below the Kong Bitu under
17、 the hydrostatic pressure to the hole collapse, and even the phenomenon of flow of sand. If you can keep the borehole wall high underground water head, increase the hole hydrostatic pressure, to prevent collapse hole, hole wall. Casing in addition to play this role, at the same time, good isolation
18、of surface water, ground, protecting the orifice pile hole drill guide fixed (4) slurry preparation Drilling mud is composed of water, clay ( bentonite ) and an additive composition. A floating drilling waste slag cooling the drill bit, drill, lubrication, increasing hydrostatic pressure, and in the
19、 hole wall to form a slurry, partition within the bore to prevent seepage, the hole collapse effect. Modulation of the drilling mud and circulating purifying mud, should be based on the drilling method and formation conditions to determine the slurry consistency, slurry consistency should be conside
20、red stratigraphic changes or operational requirements of motor control, the mud is too thin, small, poor effect of elimination of slag wall; slurry is too thick will weaken bit impact function, reduce drilling speed. (5) drilling The borehole is a key working procedure, in construction must strictly
21、 according to the operating requirements, in order to ensure drilling quality, attention must be given to the hole quality, must be opposite for this good midline and verticality, and pressed well casing. Must pay attention in the construction are continuously added and pumping the slurry slag ( imp
22、act type ), but also at any time to check whether there is deviation phenomenon into hole. Using the impulse or clamshell type drilling machine construction, soil due to vibration and impact near the adjacent hole stability. So the drilled hole should be timely cleaning hole, decentralization and po
23、uring underwater concrete reinforcing cage. Drill order should also be practical to plan, should not only guarantee a pile hole construction does not affect the last pile hole drill, and the moving distance of not too far and mutual interference. (6) the hole cleaning The drilling depth, diameter, l
24、ocation and shape of hole is directly related to the quality of pile and pile body black. Therefore, in addition to drilling process close observation supervision, to meet the design requirements in drilling hole depth, with deep, hole, pore shape, pore size and other inspections. In the end hole in