道路升级改造 施工方案 英文版.doc
《道路升级改造 施工方案 英文版.doc》由会员分享,可在线阅读,更多相关《道路升级改造 施工方案 英文版.doc(20页珍藏版)》请在三一办公上搜索。
1、1. GeneralThe scope of works in the project includes:(a) General(b) Setting out(c) Drainage Works (Including lining the trapezoidal drains with concrete or masonry) (d) Earthworks ( Grading, Forming , Embankment construction and Re-gravelling)(e) Road Paving and Surface sealing(f) Concrete works(g)
2、Road Furniture The scope of works include upgrading of the gravel road to bituminous surface dressing and drainage works. We carried out the site inspection conducted by the Client and we are very familiar with the site conditions as relates to these works.2. Project AdministrationWe shall provide,
3、maintain and subsequently remove temporary office, sanitary arrangements, store, workshop and everything necessary for the completion of the works. The site office will be provided with all the necessary facilities required including on- site test equipment to test compaction density and survey equi
4、pment to ensure that the works done are to specification. At mobilization, we will move all the necessary equipment, personnel and materials to site. This process will take only a month from the date of the commencement order.We shall employ female staff as well and shall be paid no less than the go
5、vernment gazette requirement for wages.The Consortium will provide a Contract Manager on the project who will make sure that all resources are available to the Project Staff for timely execution of the works.We shall have a Site Agent/Engineer whose duties shall include but not restricted to; progra
6、mming of the works, progressing and co-ordinating all the works. He will also be responsible for the following: All of the Contractors design (where appropriate) Construction of all road and drainage works Ensuring that all works complied with relevant standard and environment requirement. All corre
7、spondence and communication between the Employer and the Contractor, the Engineer and the Contractor shall be directed through the Contract Manager. Our proposed project organization chart is attached.1 3. Traffic ManagementA traffic Management plan will be formulated to minimize disruption of traff
8、ic flow as works progress. Alternative routes shall be opened up for motorist so as not disrupt works as well as inconvenience the motorists. We will endeavor to complete one or two roads at a time before moving to other roads so that traffic flow in town is not disrupted. Once one road is completed
9、, it will be opened to traffic to restore the flow.4. Site PreparationClearing shall consist of removal of grubbing all vegetation on the roads including disposal of all material resulting from the clearing and grubbing as directed by the supervising engineer.Only the trees within the right of way w
10、hich may fall on the carriageway or block the drainage system, or block sight lines shall be removed. 5. Method StatementKindly refer to the following Construction Sequence of Main Project: 2 5.1 Repeating SurveyAccording to the traverse points and elevation offered by supervising engineer, repeatin
11、g survey are required by means of total station instrument, involved control pile to be set every 500m along the line. All the project teams shall add piles in accordance with control pile approved by consulting engineering; test、layout centre pile and section pile, 20m in a line segment and 10m in
12、a curve segment, or set it as per requirements of consulting engineer, while test、layout the location of bridge and culvert.As per survey data outside, construction drawing shall be designed by means of software, including dimension of section、form of structure, which shall be3conducted after approv
13、ed by consulting engineer.5.2 Earthwork & Stonework Excavation and Treatment1、Earthwork Excavation: Excavator or bulldozer will be used to removed gravelly soil. Filling materials for roadbed will be delivered to the segment of filling within economical distance after the approval of consulting
14、engineer, and the remaining to be delivered to spoil ground specified (or approved) by consulting engineer. While repairing and compacting for existing roadbed, the bench excavation is applied in accordance with different types of excavation or filling. The steps and roadbed shall be compacted toget
15、her, and the thickness is not less than 150mm. After confirmed by supervising engineer, if the excavated materials can be reused, shall be stacked on specified location, and crushed to extent size as required.2. Stonework Excavation: A mall amount of excavation for weathered stone will use excavator
16、, however, blasting construction will be used for a large area of stonework excavation.5.3 Earthwork Construction for RoadbedEarthwork Construction for Roadbed will be conducted as per the following procedures “Three Stages、Four Segments、Eight Technology Process”, as follows:Three Stages: preparatio
17、n stage、construction stage、completion stage; Four Segments: filling area、leveling area、rolling area、test area;Eight Technology Process: construction preparation、basement treatment、filling in layer、paving and leveling、watering and drying、rolling and compacting、test and signature、roadbed renovation.4
18、5(1) Preparation WorkEstablishment of temporary pavement , arrangement for personnel、machinery entering the arena、waterproof & drainage facilities.Selection of Materials and Compacting Test:Compacting test shall be conducted to ensure appropriate technological parameter used in construction stag
19、e, approved by supervision. Detailed content: selection of suitable compacting machinery;selection of the best fill depth、the best water content; selection of reasonable compaction times; confirmation of earth volume in rate of change、coefficient of loose laying; confirmation of reasonable technolog
20、ical process.Survey and Positioning:Set permanent plane and vertical control point, setting out centre line by surveying in the construction area, set the location for toes of roadbed、trench and excavate it as per design position.Verifying the Geological Survey:Detailed design documents about engine
21、ering geology、hydrology and geological basis, practical situation of this project, involved the similarly construction experience of foundation, the following above items are required prior to commencement of work.It is necessary to carry out additional exploration, to inspect and calibrate geologic
22、al data based on the original geological data. Exploration will be conducted by the methods of static test and vane shear test.(2) Base of Foundation TreatmentSurface Clearing: Prior to commencement of work, attachments planted on the land、grass、tree root and other clutters shall be removed, while t
23、he thickness of clearing is not less than 0.15m, arrangement for drainage facilities as well. If base of foundation is cultivated land or loosen soil, the original surface shall be rolled and compacted, while the thickness of loosen soil is less than 0.3m; otherwise, the thickness of loosen soil is
24、more than 60.3m, which shall be loosened、crushed、 rolled & compacted based on practical situation; after that, bulldozer will be used to remove humus soil and deliver to spoil ground by dump truck. The pits and caves due to cleaning shall be backfilled by using materials (crushed stone) with bet
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 道路升级改造 施工方案 英文版 道路 升级 改造 施工 方案 英文
链接地址:https://www.31ppt.com/p-2797394.html