1、1,Advanced Planning and Scheduling,ReferencesErrington,“APS-a powerful emerging technology,”1997i2 technology product informationAdexa product informationi2 FP training materials,2,Outline,Introduction to APS Implementation of APSAPS solutionsExample of APS planning engine-FP,3,Traditional Divided P
2、rocess,Prod./Res.Planning,M.Sched.RCCP,MRPCRP,Detailed Scheduling,MASTER,EXECUTION,DRP,DemandMangmt.,DISTRIBUTION,MPS,Demand,4,Divisions of the Complex Problem,Division by planning time horizonlong-term/strategic,medium-term/tactical,and short-term/operationalDivision by different constraint concern
3、smaterial constraint/capacity constraintmanufacturing constraint/distribution constraintDivision by different detail levelsmaster production scheduling/detailed schedulingstrategic capacity planning/detailed resource planningdemand promising/due date quote,5,Deficiencies of the Traditional Process,D
4、ivisions to simplify the softwarecomplexity is minimized by breaking up the problemlocal optimums do not sum up to a global optimumburden is shifted to human plannerDivisions lead to iterationonly part of the whole problem is considered by each planning toolplan results and problems are propagated a
5、mong toolsiteration is needed to achieve a better plan qualityManual iteration is impracticalmanual effect analyses of changes mademanual judgement to make changes,6,Drivers of New Planning System,Computing power has changedhardware capability has advanced dramaticallysoftware design has advanced si
6、gnificantlyfriendly user graphical interfaces Planning problem has changed1980s competitive drivers-TQM and JIT1990s competitive drivers-responsiveness and flexibilityaccurate,real-time,dynamic planning capabilities requiredPlanning process must changeBPR/TOCenhancing the competitiveness instead of
7、automating the business process,7,Supply Chain Optimization/Foundation of eB:Advanced Planning and Scheduling(APS),Is a redesign of the overall planning process that integrates the process across several dimensionsAddresses the whole planning problem directly,rather than dealing with small parts of
8、the problem separately,8,Concurrent Planning,Customer Due Dates,PlanningEngine,Demand Forecast/Customer Orders,AvailableProductionCapacity,Raw MaterialsProcurement/Supplier Lead Times,InventoryLevels,Resources,Distribution/Warehouse Routing,Optimal Plan,9,Integrated Planning,10,The Integration of AP
9、S,Integrating master and execution planningIntegrating material and capacityIntegrating manual and automated planningMaking order promising dynamic and real-time,11,What is New in the APS,Memory-based processing and advanced algorithms to compute sophisticated production and distribution plans that
10、consider multiple constraintsSynchronize constrained resources and materials flow to a detailed levelQuick re-plans by including the latest informationRule-based logic allows users to capture their business and production strategies and priority“What-if”analysis to support decision making process,12
11、,Focuses of APS,Supply chain planningInclude some features of MRPII&ERPDevelop plan for multiple facilities,suppliers,and logisticsGoal:determine what to make and where to make,not individual operationsMulti-plant schedulingAllocate order over multiple facility and develop schedulePlant schedulingDe
12、velop detailed operation or job schedulesConsider both materials and components requirements,13,Approaches of APS,Constraint-based planning:Heuristic engine:rely on the forward and backward scheduling to balance orders against the resourcesTheory of constraints engine:identify resource bottlenecks a
13、nd then prioritize activities to minimize the bottlenecksSimulation engine:model shop floor,process local heuristic scheduling rule,and generate statistical output about the flow through work centersKnowledge-based engine:use implicit rules about customer demand,work flow,resources,and constraints t
14、o balance incoming orders against delivery dates,14,Approaches of APS(contd),Optimizer engine:use mathematical programming and branching techniques to minimize scheduling and resource conflicts in meeting individual customer ordersNetwork-based planningWork from top-down starting from customer order
15、 Schedule one customer order at a time,resolve materials and capacity issues concurrently on every operations,15,Outline,Introduction to APS Implementation of APSAPS solutionsExample of APS planning engine-FP,16,Selecting the Software,Criteria:Focus:distribution?manufacturing?type of industries?Matu
16、rity and support Feature:all key system constraints considered?Integration:easy?Seamless?Technology:latest software technology used?Platform:flexible?Price:%of revenue?Best way:use a small,but representative,set of data including all the key elements,then ask vendors to create prototypes for demo,17
17、,Implementation of APS,Business reengineering(?)Develop a model of manufacturing system using the constructs provided by the packagesIntegrate with the existing systems and data cleaningCustomizeIncluding second-party reporting software,special rules,nonstandard featureTrain users and individuals fo
18、r maintaining the system,18,Interactions between ERP/APS and MES,19,Issues of Implementing APS Solutions,APS ready?sound enterprise information system required(not necessary an enormous ERP system)APS solution is not a software package,its a way of doing business and its a universal way(everyone inc
19、luding your competitors).Are your competitive advantage compromised by implementation of SCP solutions?,20,Outline,Introduction to APSImplementation of APSAPS solutionsExample of APS planning engine-FP,21,Gartner:Process Industry Gartner Group:Magic Quadrant in Oct.99,Challengers,Leaders,Manugistics
20、,SCT/Fygr,i2,JD Edward,Logility,SAP,Adexa,Aspen Tech,Mercia,LPA,DemandMgmt,Ability to Execute,As of 9/30/99,Niche Players,Visionaries,Completeness of Vision,22,Gartner:Discrete Industry Gartner Group:Magic Quadrant in Oct.99,Challengers,Leaders,Manugistics,i2,Edwards,JD,Web Plan,Adexa,Mercia,LPA,Dem
21、andMgmt,As of 9/30/99,Niche Players,Visionaries,Completeness of Vision,Logility,Aspen Tech,Thru-Put,STG,Peoplesoft,Baan,Synquest,Ability to Execute,23,i2 TradeMatrix Solutions Overview,DesignPartners,Customers,Direct Material Suppliers,Indirect Material Suppliers,Logistics Providers,Product Developm
22、ent/Engineering,Manufacturing,Marketing/Sales/Administration,CustomerManagement,Supply ChainPlanning,Procurement,ProductDevelopment,ServiceManagement,Fulfillment,24,i2 TradeMatrix Solutions,For product development:Design Solutioncollaborated design and development for low cost,low risk and short tim
23、e-to-marketFor procurement:Buy Solutionefficient sourcing,negotiation,collaboration and ordering For supply chain planning:Plan SolutionEfficient conversion of raw material into customer-ready product offeringsFor customer management:Sell Solutionmarketing,selling,customer collaboration,order proces
24、sing and monitoringFor order promising and logistics:Fulfill Solutionintelligently commitments to customer order and requestsFor service planning and scheduling:Service SolutionIncrease of customer satisfaction and revenue with minimum investment,25,i2 TradeMatrix Plan Solutions,tactical,buy,make,mo
25、ve,sell,store,strategicbusiness&networkplanning,messaging and data integration,demand planning/inventory&sop planning,manufacturing planning,scheduling,distribution/inventory planning,transportation,configuration,command&control,strategic,operational,execution,26,i2 TradeMatrix Plan Solution,DemandP
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- i2 aps培训-高级计划排成2 aps 培训 高级 计划 排成

链接地址:https://www.31ppt.com/p-2667291.html