EPC(设计、采购、施工)项目实施计划EPC PROJECT EXECUTION PLAN.doc
《EPC(设计、采购、施工)项目实施计划EPC PROJECT EXECUTION PLAN.doc》由会员分享,可在线阅读,更多相关《EPC(设计、采购、施工)项目实施计划EPC PROJECT EXECUTION PLAN.doc(66页珍藏版)》请在三一办公上搜索。
1、EPC PROJECT EXECUTION PLANEPC(设计、采购、施工)项目实施计划目 录Table of ContentsPROJECT EXECUTION PLAN10. 项目组织机构3Project Organization Chart31. 设计管理4Design Management41.1 设计资源5Design Resources51.2 设计控制6Design Control61.3 设计中的安全和可操作性方面的考虑6Considerations of Safety and Operational Ability in the Design61.4 设计外部接口及相关建议
2、7Designed External Interface and Related Suggestions71.5 设计变更管理9Design-change Management91.6 设计过程的关键会议10Key Meetings During Design Process102. 采购策略13Procurement Strategy132.1 采购方针13Procurement Guideline132.2 采购范围13Scope of Procurement Works132.3 采购组织机构及人员设置13Structure and Personnel of Procurement Or
3、ganization132.4 采买工作程序及进度14Procurement Procedure and Schedule143. 施工管理策划23Constructive Management Plan233.1 概述23Outline233.2 xx项目xx工程项目主要工程实物量23Main constructive work volume of 业主单位 Xx Complex project XX tanks project233.3 xx项目xx工程施工管理目标23Target of 业主单位 Xx Complex project XX tanks works constructive
4、 management233.4 现场施工阶段的工作划分28Partitioning the work at site construction stage284. HSE计划34HSE Plan344.1 HSE 总则34HSE General Rule344.2 HSE目标34HSE Target344.3 HSE组织机构图与职责35HSE Organization And Its Obligations354.4 安全会议40Safety Meeting404.5 工作危险性分析41The Analysis of Work Danger414.6 安全检查42Safety Inspect
5、ion424.7 事故的隐患控制43The control of the potential accident434.8 事故/意外事件的调查分析46The investigation of incident/accident464.9 消防措施47Fire Protection Measures474.10 急救、医疗设施和医疗保险措施48First Aid, Medical Facilities And Medical Insurance Measures484.11 个人劳动防护49Personal Protective Equipment494.12 环境保护50Protection
6、of Environment504.13 分承包商的控制50The Control of Subcontractor504.14 保卫计划51Safeguard Plan510.项目组织机构Project Organization ChartEPC单位为了确保项目xxxxxx石化xx项目EPC的顺利实施,特组建项目部,代表EPC单位履行项目合同,项目组织机构及主要人员如下:In order to ensure the Xxxx Petrolchemicals Project-Xxt Tanks being executed and completed smoothly, a Project T
7、eam is established on behalf of EPC单位 to perform the EPC contract. The organization chart of project team is as below:项目经理 Project Manager控制经理Control Manager项目副经理Deputy Project ManagerQA/QC经理QA/QC Manager合同经理Contract Manager采购经理 Procument Manager设计经理 Design Manager财务经理 Fanancial Manager施工经理Construct
8、ion ManagerHSE经理 HSE ManagerIT经理 IT Manager防腐绝热施工队Anti-corrupt & Insulation Construction Team安装施工队Installation Construction Team土建施工队Civil Work Construction Team1. 设计管理Design Management设计工作在项目实施的全过程中起关键作用。工程设计图纸和文件是项目实施过程中后续几个阶段(采购、施工、开车)的主要依据。设计管理与控制是项目管理全过程中的一个重要方面。设计管理和控制水平的高低,直接关系到项目的进度、费用、质量和材料
9、的控制水平。Design work plays a key role in the whole process of project implementation. Drawings and documentation of engineering design constitute the main basis for the subsequent stages (procurement, construction, start-up) in the process of project implementation. Design management and control is als
10、o of great importance in the whole process of project management. The level of design management and control directly affect the level in control of project progress, cost, quality and material.为了平稳和有效的进行设计工作,EPC单位将组织一个由项目设计经理领导的设计组来完成有关的设计工作。设计工作将由设计单位和设计单位共同进行,EPC单位将充分利用其现有的资源和有经验的人员来支持项目的实施。这些人员将
11、根据需要直接或间接参与工作。为便于信息的交流,设计组将采用相同的软件工具和标准化的方法工作。项目管理组定期监督设计质量体系执行情况。In order to smoothly and effectively carry out the design, EPC单位 will organize a design team led by the project design manager to perform the relevant design work. The designed will carry out together by 设计单位 .EPC单位 will make full use
12、 of its existing resources and experienced personnel to support the project implementation. These personnel will directly or indirectly participate in the work as needed. In order to facilitate the information exchange, the design team will do the work with the same software and tools in a standardi
13、zed way. The project management team will regularly supervise the implementation of design quality system.在详细设计阶段,设计组将与业主的 业主单位和PMC保持良好的协调关系,以确保项目的有效和及时的执行。At the detailed design stage, the design team will keep a good coordination with the Owners 业主单位&PMC to ensure the effective and timely implemen
14、tation of the project.以下是项目设计组织框图:The organization chart for the project design is shown below.lue1.1 设计资源Design ResourcesEPC单位设计部已有覆盖各专业的计算机应用网络系统,可通过设计局域网、INTERNET和PROJECTNET实现信息共享和通讯。先进的IT系统将在设计中使用。用于计算、制图以及数据处理的先进计算机将支持设计工作。EPC单位 Design Department has possessed a computerized application network
15、 system covering various trades, which can realize the information common share and communication via the designed LAN, PROJECTNET as well as INTERNET. The advanced IT system will be used in the design and the up-to-date computers used for computing, plotting and data processing will give a support
16、to the design.EPC单位在以往的工程设计中已成熟应用的软件有:工厂设计系统PDS、管道应力分析软件CESAR II、有限元分析软件ANSYS、钢结构计算软件STAAD/PRO、AutoCAD R14/R2000专业绘图软件和各专业自行开发的一批实用设计软件百余套,并且拥有熟练的软件应用人员。Following are the software packages EPC单位 applied maturely in the past engineering designs. They include: plant design software PDS, piping stress
17、analysis software CESAR II, pressure vessel design and computing software LANSYS, steel structure computing software STAAD/PRO, AutoCAD R14/R2000 professional plotting software and more than 100 sets of practical design software developed by different professions. EPC单位 has also owned skilled softwa
18、re application personnel.本项目主要设计软件有:TANK software version:95.2 大型储罐计算程序; API-650/653 Analysis software version:2.4 (授权号:TANK License#18xx0); 钢制双向子午线网壳计算程序PROSPAMain design software for this project include:TANK software version:95.2 large scale tank calculation procedure; API-650/653 Analysis softwa
19、re version:2.4 (Authorised No.:TANK License#18xx0); Steel double directional meridian dome roof calculation sofeware PROSPAEPC单位的设计人员掌握适用的、有效的石油化工项目国内、国际设计标准和规范。在项目发展过程中,计算机软件将用于所有涉及到的设计工作,例如: 罐体计算准备,土建和结构计算等。Designers in EPC单位 know well the domestic and international design standards and codes appl
20、icable and effective for petrochemical projects. In the process of project development, computer software will be used in all design work involved in, for example, xxxx of tank calculation preparation, civil work and structural computation, etc. 1.2设计控制Design ControlEPC单位两个设计部门设计单位和设计单位建立了完善的设计控制程序,
21、从设计策划、设计输入、设计评审、设计验证、设计确认、设计输出到设计变更各个环节,都有相关的工作规定。EPC单位将在由PMC编写的 xx罐区基础工程设计文件及对基础工程设计文件的审查意见的基础上, 展开xx罐区工程EPC单位承担部分的所有详细设计工作。Two design department 设计单位 and 设计单位 in EPC单位 has established the perfect procedures for design control, including specific rules related to different links of the chain from t
22、he design planning, design input, design review, design verification, design confirmation, design output to design modification. On the basis of xxt tanks fundamental engineering design document prepared and the examination comments given by PMC to the document, EPC单位 will make all the detailed desi
23、gn for its undertaking part in the xxt tanks project.为了支持施工计划进度的实施,xx罐区工程设计和相关工作的次序需要仔细进行组织调整,以满足xx罐区工程总进度的要求。In order to support the implementation of scheduled construction plan, the sequence for the xxt tanks engineering design and relevant work needs to be carefully organized and adjusted to mee
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- EPC设计、采购、施工项目实施计划EPC PROJECT EXECUTION PLAN EPC 设计 采购 施工 项目 实施 计划
链接地址:https://www.31ppt.com/p-2398925.html