【经营企划】杜邦she审核英文报告.doc
《【经营企划】杜邦she审核英文报告.doc》由会员分享,可在线阅读,更多相关《【经营企划】杜邦she审核英文报告.doc(6页珍藏版)》请在三一办公上搜索。
1、 Evaluation For Safety, Health, Environmental(June 23, 2003)A site evaluation of SHE was conducted of Procedures, Systems, Field Area tours, spot interviews, and records. Ding Ming Guan - Asia Sourcing Center, Sourcing SpecialistSummary:The team based on Chinese regulations and had reference of Dupo
2、nt SHE standards and industry best practice guideline (NFPA) .In general terms, the operation only aligns with minimum essential with intent to meet regulations. However, it appears they do not monitor regulation upgrades and appear to be out of regulation in areas from lack of knowledge or understa
3、nding.Since the site could not supply all consent to operate documentation nor data, and the most managers are absence, we can not assess whether or not current operation fully meet regulations. An assessment of current operations against regulations for such items as the operators of fork lift truc
4、k and welding are without permits from the local government.Conclusion: The SHE evaluation study has identified several areas that need improvement. These improvements primarily require changes in work practices, procedure development, training of personnel and the operational discipline to insure c
5、onsistent implementation.However: The site should be requested the following for confirmation during business negotiation.The all operators with special hazards job which governmental required should attend the proper training and get the permits from the government agency.The most SHEA procedures n
6、eeds to be updated for covering all regulation requirements and keep operational discipline.Safety and Fire ProtectionThey have the policy of safety which be posted on the wall, the most safety procedures are in general and not cover all regulation requirements such as fire protection management. Th
7、ere are not important procedures in place such as Lock Tag Try and Confined space work procedures. The operational procedures are not integrated SHE requirements and elements such as PPE required. Two contractors are painting the floor in the workshop without work permit and being monitor. There are
8、 not contractor management procedure in place.One operator showed his personal respirator , I was said that he did not receive proper trained for using and maintenance. The host claimed that there were not any injuries and fire cases. But we noted one switch was burned in the warehouse.We noted that
9、 the walkway in No. 1 Workshop and gates was obstructed by products and package material. The damaged plates were stored in disorder under the crane.I checked one operator of the fork lift truck, he said that he had not got the permit and he claimed to inspect the fork lift truck daily but could not
10、 show us the records.I checked one operator of welding, he said that he had not got the permit also.We noted that the cylinders of oxygen and fuel were stored together. There three works are worked in storage area without any sign to warn for the repair work.I noted that four workers loaded the prod
11、ucts on the road, I was confirmed that this was normal work.The warehouse was full stored by package material and products and oil.There are exit sign and emergency light in office building, but without it in workshop and lab and warehouse.The site has sprinkler, detection nor alarm systems in the o
12、ffice building but without it in workshop and warehouse and lab. Their fire protection system consisting of some fire extinguishers and depends on local fire agency response. I was informed that they have emergency response organization, but they could provide limited related records.The government
13、fire brigade agency is very close to the site, it is about 5minutes for the distance. The site did not set up process safety management system, and did not conduct process hazards analysis or consequence analysis.The site provide one permits of handling hazards chemicals on site from fire protection
14、 agency, but could not provide any documents of hygiene administration agency approved for the facility.The site could not provide any design base of the facility, so it is difficult to ensure this facility meet all of the fire safety and protection codes required by governmentFlammable reagents was
15、 stored in lab without secondary containment and will need to be installed.General field observations indicated a weak preventative maintenance program and few or inadequate equipment guards for rotating equipment.Recommendation:An immediate training and awareness program would be needed. The site s
16、hould obtain the information of the facility design base and the documents of fire protection and hygiene administration agency approved for the facility. The site should conduct a formal process hazardous analysis and list a action plan to control the risk of safety and fire protection. An inventor
17、y of equipment guarding will need to be developed, prioritized and implemented. The site should consider how to eliminate the risk at the source, to ensure the facility is inherent safety. Process Safety Management (PSM)The site could not provided the information of design base for the boilers syste
18、m. Emission data was not available to determine whether the facilities are operated in compliance.The site did not set up the management systems program and/or procedures for process safety management.The site could not provide block flow diagram or simplified process flow diagram.The site has not c
19、onducted a process hazardous analysis.The site could not provide any procedures or information to align with audit checklist for PSM elements in Technology, Personnel, and Facilities.The site never conduct sitewide emergency drills. The site conducted extinguisher using exercise on field in annually
20、, but, they could not provide the related records.Recommendation:The site should obtain the information of design base for the key process equipment, such as the boiler system and the storage tanks of LPG. The site should set up the PSM system, and develop procedures and audit checklist for PSM elem
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 经营企划 经营 企划 杜邦 she 审核 英文 报告
链接地址:https://www.31ppt.com/p-2351985.html