项目管理双语ppt课件第六章成本管理.ppt
《项目管理双语ppt课件第六章成本管理.ppt》由会员分享,可在线阅读,更多相关《项目管理双语ppt课件第六章成本管理.ppt(77页珍藏版)》请在三一办公上搜索。
1、Resource PlanningCost EstimatingCost BudgetingCost Control,Processes required to ensure the project is completed within the approved budget,Chapter 6 Project Cost Management,Cost Management,7.1ResourcePlanning,Planning,7.3Cost Budgeting,7.4CostControl,Controlling,7.2Cost Estimating,Resource Planning
2、,Determining physical resources needed (i.e., material, equipment, and people) and what quantities of each should be used and when they would be needed to perform project activities,Resource Planning,Inputs Scope statementWBSResource pool descriptionOrganizational policiesHistorical informationActiv
3、ity durations estimates,Tools & TechniquesExpert judgmentAlternatives identificationPM software,OutputsResource requirements,Inputs,Work breakdown structure (WBS) Identifies the project elements that require resources Historical information Used to identify the types of resources that were required
4、for similar work on previous projects Scope statement Contains project justification and the project objectives, which need to be consideredResource pool description Description of resources available, if necessary, to work on a projectOrganizational policies Of the performing organization, regardin
5、g staffing and the rental and purchase of supplies and equipmentActivity duration estimates,Resource Planning,Tools & Techniques,Expert judgment Expertise, provided by any group or individual, used to assess the inputs to this processOther units within organizationConsultantsProfessional and technic
6、al associationsIndustry groupsAlternatives identification PM software Used to organize resource pools, define resource availabilities and rates, and define resource calendars,Resource Planning,Outputs,Resource requirements Description of the types (e.g., skill levels) and numbers of resources requir
7、ed by each element of the WBS,Resource Planning,Cost Estimating,Difference between cost estimating and pricing:Cost estimating: Assessing how much it will cost the organization to provide the product or servicePricing: Assessing how much the organization will charge for the product or serviceCost es
8、timating also includes identifying and considering cost alternatives,Process of developing an approximation (or estimate) for the cost of the resources necessary to complete the project activities,Cost Estimating,Inputs WBSResource requirementsResource ratesActivity duration estimatesEstimating publ
9、icationsHistorical informationChart of accountsRisks,Tools & TechniquesAnalogous estimatingParametric modelingBottom-up estimatingComputerized toolsOther cost estimating methods,OutputsCost estimatesSupporting detailCost management plan,Inputs,WBS Used to organize the cost estimates and to ensure th
10、at the cost of all identified work has been estimatedResource requirements Resource rates Unit rates for each resource Activity duration estimates Affects cost estimates if project budget includes an allowance for the cost of financing (i.e., interest)Chart of accounts Coding structure used by the o
11、rganization to report financial information. Cost estimates must be assigned to the correct accounting category.,Cost Estimating,Inputs (cont.),Historical information Information on the cost of resourcesProject files Records of previous project results that are detailed enough to aid in developing c
12、ost estimatesCommercial cost-estimating databases Historical information available commerciallyProject team knowledgeEstimating publications Commercially available data on cost estimatingRisks Since risks can have a significant impact on cost, the effect of risk on the cost estimates for each activi
13、ty must be considered,Cost Estimating,Tools & Techniques,Analogous estimating (Expert judgment) Used to estimate total project costs if there is a limited amount of detailed information Parametric modeling Using project characteristics (or parameters) in a mathematical model to predict costs (e.g.,
14、price per square foot)Bottom-up estimating Estimating the cost of individual work items and then rolling up the costs to arrive at a project totalComputerized tools PM software and spreadsheets,Cost Estimating,Outputs,Cost estimates Quantitative assessments of the cost of resources (e.g., units of c
15、urrency or staff hours) Types of estimatesOrder of magnitude (-25% / +75%)Budget estimate (-10% / +25%)Definitive estimate(-5% / +10%)Supporting detailDescription of estimated scope of workDocumentation of the basis for the estimateDocumentation of any assumptions madeRange of possible results,Cost
16、Estimating,Outputs (cont.),Cost management planDescribes how cost variances will be managedPart of the overall project plan,Cost Estimating,Cost Budgeting,Allocating the overall cost estimate to individual activities or work packages, in order to establish a cost baseline for measuring project perfo
17、rmance,Cost Budgeting,Inputs Cost estimatesWBSProject scheduleRisk management plan,Tools & TechniquesCost-budgetingtools and techniques,OutputsCost baseline,Inputs,Cost estimates WBS Identifies the project elements to which the costs will be allocatedProject schedule Used to assign costs to project
18、elements for the time period when costs will be incurredRisk management plan Often includes cost contingency, which can be determined on the basis of the expected accuracy of the estimate,Cost Budgeting,Tools & Techniques,Cost budgeting tools and techniquesAnalogous estimatingParametric modelingBott
19、om-up estimatingComputerized tools,Cost Budgeting,Outputs,Cost baseline Time phased budget that will be used to measure and monitor the cost performance of the project,Cost Budgeting,Cost Control,Includes:Monitoring cost performance to detect variances from the planEnsuring that all appropriate chan
20、ges are recordedPreventing incorrect, inappropriate, or unauthorized changesInforming the appropriate stakeholders of authorized changesAnalyzing positive and negative variances and how they affect the other control processes,Influencing the factors that create changes to the cost baseline to ensure
21、 that changes are agreed uponDetermining that the cost baseline has changedManaging the actual changes when and as they occur,Cost Control,Inputs Cost baselinePerformance reportsChange requestsCost management plan,Tools & TechniquesCost change control systemPerformance measurementEVMAdditional plann
22、ingComputerized tools,OutputsRevised cost estimatesBudget updatesCorrective actionEstimate at completionProject closeoutLessons learned,Inputs,Cost baselinePerformance reports Information on cost performanceChange requests Oral or written requests to change the budgetCost management plan,Cost Contro
23、l,Tools & Techniques,Cost change control system Procedures used for making changes to the cost baselinePaperworkTracking systemApproval levelsPerformance measurement Assessment of the magnitude of any variation, the cause of the variance, and the corrective action needed,Cost Control,Tools & Techniq
24、ues (cont.),Additional planning Changes may require new or revised cost estimates or an analysis of alternative approachesComputerized tools Used for tracking the value of planned costs compared to actual costs and for predicting the effects of cost changesEarned Value Management Continuously measur
25、ing project performance by relating the planned value, the earned value for work accomplished, and the actual costs incurred,Cost Control,Outputs,Revised cost estimatesBudget updatesCorrective actionEstimate at completion Forecast of most likely total project costs based on project performance and r
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 项目管理双语ppt课件第六章 成本管理 项目 管理 双语 ppt 课件 第六 成本
链接地址:https://www.31ppt.com/p-1800342.html